6 START-UP
Start-up sequence
Unit power supply ON
Yes / No
1 compressor carter resistances operating at least since 8 hours
2 off-load voltage measure
3 phase sequence check
4 pump manual start-up and flow check
5 refrigeration circuit shut-off valves opening (if applicable)
6 unit ON
7 load voltage measure
8 verify the lack of bubbles in the liquid light (if applicable)
9 check of all fan operating
10 measure of return and supply water temperature
11 super-heating and sub-cooling measure
12 check no anomalous vibrations are present
13 set-point personalization
14 scheduling customisation
15 complete and available unit documentation
Содержание R513A
Страница 1: ...R513A MANUAL FOR INSTALLATION USE AND MAINTENANCE WDAT ik4 120 1 580 2 MF500002 00 11 20...
Страница 20: ...20 5 ELECTRICAL CONNECTIONS...
Страница 34: ...34 7 CONTROL...
Страница 35: ...35 7 CONTROL...
Страница 36: ...36 7 CONTROL...
Страница 37: ...37 7 CONTROL...
Страница 51: ...51 9 ANTIVIBRATION MOUNTS Anti vibration mount support Anti seismic spring antivibration mounts...
Страница 52: ...52 9 ANTIVIBRATION MOUNTS...
Страница 53: ...53 9 ANTIVIBRATION MOUNTS...
Страница 73: ......