Installation Guide_PV-ezRack_SolarTerraceIII-A_AU_V2.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
26
page
of 28
Installation Instruction
5.4.2 According to the installation planning,
use Total Station (or any instrument of similar
functions) to mark out the piling positionof
each Ground Screw. Check the marked
positions before piling, to ensure accuracy.
Piling depth, horizontal and vertical position
of Ground Screwsare determined by the
engineering drawings of the specific project.
5.4.3 Ensure all Ground Screws are on the
same level and aligned as per the diagram
below.
Fig. 31
If cannot eliminate the deviation of Ground Screw, its
maximum allowable deviation should in the range of
adjustment shown in below Figure24.
Fig. 32
33
The maximum allowable connection deviation of the
Ground Screw to the Support should be within the
range of adjustments shown in Figure33 below.