Installation Guide_PV-ezRack_SolarTerraceIII-A_AU_V2.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
25
page
of 28
Installation Instruction
5.3.3 Apply one pre-assembled Grounding Lug
per T Rail. Click the Grounding Lug into to the
channel of the T Rail and insert the Copper Wire.
(the maximum size is 6AWG or similar) Then
fasten the bolt M6*14 with 10N.m and fasten
the bolt M8*25 with 13.5N.m as shown in the
Figure28.
Step 6 Repeat the above steps to install all PV Modules. Visually check the Universal Clamps and PV
modules are properly positioned and then tighten all Clamps.
The recommend torque for Universal Clamps that are used as End Clamps is 13~14N.m.
The recommend torque for Universal Clamps that are used as Inter Clamps is 18~20N.m.
5.3.4 Now the installation is completed as shown in Figure 29. Please recheck all Bolts and fasten
them tightly according to the recommended torque.The PV Modules should be aligned correctly with
18mm gaps when using End and Inter Clamps and 20mm gaps when using Universal Clamps.
Fig. 28
Fig. 29
5.4.1 Before the installation, please prepare
the necessary installation tools & products,
and ensure that the hydraulic pile driver
can work normally at the installation site.
Read the relevant engineering documents
to get the project layout information such as
piling depth, column span, etc. If you have
any questions, please contact and consult
Clenergy customer service.
5.4 Ground Screw Installation(Alternative to a Concrete Base and dependent on the
system design)
Fig. 30