Section 5 — Commissioning
Hawk 1000
5-2
Part No. 750-366
5.1 Commissioning the Actuators
When system configuration is complete, the <Calibrate Actuators> button will be available on the Main
screen and will indicate “Required”.
Figure 5-1. Actuator calibration required
Press <Calibrate Actuators> for the Actuator Commissioning screen, where air, fuel, and FGR actuators can
be individually selected for commissioning. On this screen, press <Commission Actuator> for the desired
actuator and read the warning screen which follows. In this example we will be commissioning the air
actuator.
Figure 5-2. Actuator commissioning
NOTE: Any combustion curves previously stored for the current fuel will be erased once the actuator
commissioning process has begun.
Press <Enable Air Actuator Commissioning> on the warning screen to
continue.
First select the direction of rotation of the actuator shaft. This is the direction of rotation to open the actuator
when looking at the actuator from the perspective of the actuator circuit board (or circuit board cover).
Actuator Commissioning Screen
Warning
Содержание Hawk 1000
Страница 1: ...750 366 07 2013 Hawk 1000 Boiler Control Operation Manual...
Страница 4: ......
Страница 6: ......
Страница 30: ...Section 3 Hardware Checkout Hawk 1000 3 12 Part No 750 366...
Страница 54: ...Section 4 System Configuration Hawk 1000 4 24 Part No 750 366...
Страница 78: ...Section 6 Diagnostics and Troubleshooting Hawk 1000 6 6 Part No 750 366...
Страница 82: ...Section 7 Parts Hawk 1000 7 4 Part No 750 366...