CLEARSPAN
™
POLY BUILDINGS
26
Revision date: 12.08.15
3. Repeat steps and continue to assemble and feed PVC
conduit into pocket.
4. Once conduit is fully assembled, secured at all joints,
and inserted into pocket, repeat steps to install conduit
at other end of cover.
5. Return to one end and cut access notches in stretch
hem pockets for strap installation.
INSTALL PVC CONDUIT (CONTINUED)
6. Verify cover is centered on frame (side-to-side and
end-to-end) and move to one end rafter.
8. Move to cover end opposite the temporary straps and
cut notches in stretch pocket as prevously described.
9. Next, take one end of the bulk roll of 1" strapping and
weave it around end rafter and PVC conduit as shown.
Photo shows how to weave strap between end rafter and
PVC conduit. (Cover and rafter shown differs from actual
cover.) Maintain an even distance between conduit the
pocket and end rafter as strap is installed.
10. Continue weaving strap around end rafter and PVC
conduit working up and over rafter and down to other
end of PVC conduit.
NOTE:
Keep strapping snug during this step, but do not
over tighten. Also, maintain a even distance between
the top of the end rafter and the PVC conduit.
11. After weaving strapping, cut strap and tie it to frame to
temporarily secure it.
12. Take remainder of bulk strap roll, move to other end of
the frame, and repeat steps to weave strap between
the PVC conduit and top of end rafter.
NOTE:
The temporary rope or straps at this end can be
removed once main strapping is in place.
13. After strap is completely installed at this end, cut strap
to length and tie it to frame.
Space notches
18" to 24" apart
on-center.
Dashed line
shows position
of conduit in
stretch pocket.
End Rafter
PVC conduit in
notched pocket
Temporary
strap or rope
Main Cover
Bonnet
18"- 24"
7. Take rope or strap and cut a few sections long
enough to tie PVC conduit to end rafter in evenly
spaced locations. See photo above.
End Rafter