Step 6: Installing the Software
Check Point 61000 Security System Getting Started Guide R75.40VS for 61000 | 54
4.
Select
Network Connections
.
For the management interface, configure:
An IP address
The net mask length
5.
Configure
Routing
.
•
If you are directly connected to the management interface: Skip this step.
•
If you are not directly connected to the management interface: Define a route which will
allow you to access the 61000 Security System.
6.
Click
Next
until you finish the installation wizard. At the SIC stage, enter a dummy key.
Configuration settings are applied, and the Security Gateway Modules reboots. Other Security
Gateway Modules in the Security Group are installed automatically.
Validating the Initial System Setup
To make sure that the initial system setup is completed successfully:
•
Run the
asg monitor
command. An
Initial Policy
must be installed on the local SGM after
initial setup completes and the SGM reboots.
•
To monitor the automatic installation of other SGMs, run:
# tail -f /var/log/start_mbs.log
•
Wait until the installation process is complete.
The installation process is complete when all the SGMs in the security group are
UP
and in the
Initial Policy
state.
SCP password for SSM160 firmware installation
https://www.checkpoint.com/support-services/contact-support/
. All
firmware installations should be performed with the assistance of the Check Point Support.