20
Operation
Product Manual - Trifecta
®
Pro Series
SETPOINT DATA ENTRY Popup
Fill Inches
field — The level to fill tanks to
Pressure Build (PB) On
— The pressure at which to begin
Pressure Build on Primary Tank
Default Bulk Critical
— Displays Bulk Tank Pressure at
which Trifecta will only vent to atmosphere
Reset
— Resets setpoints to default settings
INFO Popup
PLC Rev
field — Revision of PLC Program running on unit
HMI Rev
— Revision of HMI Program running on Trifecta
Trifecta Service #
— Chart Customer Service phone number
Serial Number
— Serial number of the Trifecta
Current PLC Program
— Current recipe running on the
Trifecta PLC
User
— User currently logged into unit
Enclosure Temp
— Temperature inside of the Control Panel
SCREEN MENU NAVIGATION Popup
ACTIVE SETPOINT Screen
Pressure Build (PB) Off
field — The pressure at which
Pressure Build will stop
Reserve PB On
— The pressure at which to begin PB on
Secondary Tank if not assisting
Reserve PB Off
— The pressure at which PB of Secondary
Tank will stop
Fast Drop PB Setpoint
— The pressure at which to begin
Pressure Build if Pressure is dropping fast
Primary Too Low to get an assist
— The level at which the
primary tank will automatically switch to the secondary tank
(low level value is programmed into the hard sets of the PLC)
Secondary Too Low to Assist
— The level at which the
Secondary Tank is too low to assist the primary tank (75% of
the current liquid level setpoint) and a primary tank switch
will occur
Level SP -1 .5
— The adjusted fill level if pressure in
Secondary Tank is greater than 130 psi at the end of the fill
cycle
Level SP +1 .5
— The adjusted fill level in pressure in
Secondary Tank is less than 80 psi at the end of the fill cycle
Bulk Tank Level Snapshot
— The point at which the PLC
takes a snapshot of the bulk tank pressure to determine when
to turn on and off the vent to atmosphere during the filling
process
Vent to ATM on SP (initial depressurization)
— The
pressure at which a Secondary Tank will begin Vent to
Atmosphere if it drops below
Vent to ATM Off SP (while filling)
— The pressure at
which a Secondary Tank will stop Venting to Atmosphere if
it drops below
Vent Low Loss SP (while filling)
— The pressure at which a
Secondary Tank will resume Venting to Atmosphere if it rises
above
Содержание Trifecta Pro Series
Страница 2: ......
Страница 20: ...16 Installation Product Manual Trifecta Pro Series...
Страница 28: ...24 Operation Product Manual Trifecta Pro Series Mode 0 Figure 1 Filling Mode Vent to Storage...
Страница 29: ...25 Operation Product Manual Trifecta Pro Series Mode 0 Figure 2 Filling Mode Vent to Atmosphere...
Страница 30: ...26 Operation Product Manual Trifecta Pro Series Mode 0 Figure 3 Filling Mode Liquid Flow...
Страница 31: ...27 Operation Product Manual Trifecta Pro Series Mode 0 Figure 4 Filling Mode Low Loss...
Страница 32: ...28 Operation Product Manual Trifecta Pro Series Mode 0 Figure 5 Filling Mode Low Loss Vent to Atmosphere...
Страница 33: ...29 Operation Product Manual Trifecta Pro Series Mode Switch 0 to 1 Figure 6 Fill Mode Termination...
Страница 35: ...31 Operation Product Manual Trifecta Pro Series Mode Switch 1 to 2 Figure 8 Secondary Maintains Hold Pressure...
Страница 36: ...32 Operation Product Manual Trifecta Pro Series Figure 9 Primary Pressure Build Mode 2...
Страница 37: ...33 Operation Product Manual Trifecta Pro Series Figure 10 Primary PB Off Mode 2...
Страница 38: ...34 Operation Product Manual Trifecta Pro Series Figure 11 Call for Assist Mode Switch 2 to 3...
Страница 39: ...35 Operation Product Manual Trifecta Pro Series Figure 12 Secondary Assist of Primary Assist Mode 3...
Страница 40: ...36 Operation Product Manual Trifecta Pro Series Mode Switch 3 to 2 Figure 13 Assist Complete Primary Restored...
Страница 44: ...40 Operation Product Manual Trifecta Pro Series...