SITE ACCEPTANCE CHECKLIST
(continued)
7. FLEXIBLE WAVEGUIDE
Overall flexible WG length:
Flexible WG type:
Flexible WG is connected securely to RFU and Antenna
OK
Flexible WG connector is weather-proofed (sealed) at the
RFU
OK
At the RFU, the flexible WG has a service/drip loop to
prevent moisture from entering the connector
OK
Flexible WG is secured using suitable restraints to fixed
points at regular intervals (0.5 m recommended)
OK
Flexible WG has no sharp bends, kinks, or crushed areas.
All bends are per manufacturer specifications
OK
Flexible WG point-of-entry to building/shelter is weather-
proof
OK
Flexible WG ends are properly labeled
OK
8. INDOOR UNIT (IDU)
IDU is securely mounted to the rack
OK
IDU is located in a properly ventilated environment
OK
IDU fans are functional and air flow to the fans is not
disrupted
OK
IDU and rack are grounded as per site specifications
OK
Traffic cables and connections are properly terminated as
per manufacturer/cable instructions
OK
All cabling is secured, tidy, and visibly labeled
OK
9. DC POWER SUPPLY
Measured DC voltage input to the IDU:
(-40.5 to -60 VDC)
Power-Supply maximum current:
(at least 3 Ampere in 1 +0 site)
Power-Supply is properly grounded
OK
DC power backup type:
IDU DC connector is secure and the DC input leads are
correctly terminated (no bare wires are visible)
OK
IDU DC connector (+) and (GND) leads are shorted and
GND is grounded
OK
10. RACK INSTALLATION
Rack is mounted to the shelter floor with four screws
OK
Rack is mounted to the shelter wall with two screws
OK