9.5 FA-20 Key stroke, serial meters and dial-back. 
 

It  is  possible  to  activate  serial  reading  of  up  to  3  serial  meters  through  a  key  stroke.  There 
may only be mounted one meter pr. serial port. When the key in FA-20 is activated for more 
then 1 second (programmable from the main station), the FA-20 will try to retrieve data first 
from a serial meter connected port M1, hereafter a serial  meter connected port M2 and at last 
from a serial meter connected port “MULTI”.  

 

After  the  keystroke  the  big  green  LED  will  blink  shortly  once  every  second  while  reading 
possible meter on port M1 and twice every second while reading possible meter on port M2 
and three times shortly per second while reading possible meter on port “MULTI”. If a meter is 
not  connected  or  of  some  reason  cannot  be  read  correctly  by  the  FA-20  –  then  the  big  red 
LED  will  light  up  for  3  seconds  –  just  as  the  FA-20  gives  up  of  getting  an  answer  from  the 
meter.  

 

If the key does not work or if not all 3 ports are tested by key stroke – then it is likely that it is 
the  main  station  who  has  commanded  the  FA-20  not  to  do  a  serial  communication  on  the 
questioned ports. (This can be relevant if FA-20 only is used for pulses). The installer can get 
around  this  by  switching  off  the  FA-20  in 5  seconds  –  then  the  FA-20  will  go  into  “engineer 
mode” where all 3 ports are read on key stroke – whether the main station has asked the FA-
20  not  to  read  one  or  more  ports.  “Engineer  mode”  ends  automatically  after  20  minutes  of 
“power failure”. 
 
If FA-20 is coded to carry out a GSM-communication (dial-back) then FA-20 will try this after 
any serial meters have been attempted to be read due to key stroke. The big green LED will 
light constantly during the communication and in case of error the red LED will report the error 
by a 3 second long flash.  
 

Note: Automatic readout after power up.  

 
Approximately 2-3 min. after power-up the FA-20 will normally begin to readout possible serial 
meters which may be connected to the FA-20. This results in the same way as when the FA-
20  reads  out  the  serial  meter  because of  key  stroke,  that the  big  green  LED flashes  shortly 
once every second by readout of possible meter on port M1 and shortly twice every second 
by  readout  of  possible  meter  on  port  M2  and  shortly  three  times  per  second  by  readout  of 
possible meter on port MULTI. If a meter is not connected or for some other reason cannot be 
readout correctly by the FA-20 – then the big red LED will flash for 3 seconds.  
 
By keystroke there will only be tried once per meter – unlike when the FA-20 per routine or 
after  power  up  tries  it-self,  where  there  typically  is  used  1-2  retries  (programmable from  the 
main station) in case the meter does not answer the first time. 

 

 

Deactivation of communication with serial meters.  

 
It is possible for the main station to deactivate the readout of serial meters both in connection 
with keystroke and in connection with power up. This can be relevant in connection with FA-
20, who alone is used for pulse counting. This can seem unfortunate if an installer later has to 
install a new extra meter and for example M2 no longer can be activated via keystroke. That 
is why there is made an exception “Engineer mode”, so that a keystroke in the first 20 minutes 
after power up ALWAYS looks for meters on all 3 serial ports if at least one port is enabled. If 
all ports are disabled for example if only pulse are received, then key stroke does not enable 
serial readings in the first 20 minutes after power up.

 

 
 

Specifications are subject to revision without notice.

 

 

Содержание FA-20

Страница 1: ...RS SMS based remote metering 1 FA 20 in brief 2 Product information 3 Installation Instructions Rev 2013 02 01 CB Svendsen A S Kirke Vaerloesevej 22 24 DK 3500 Vaerloese Denmark Phone 45 4448 5286 Fax...

Страница 2: ...lses can be freely mixed FA 20 is delivered preprogrammed with a number of serial meter drivers supporting different serial manufacturer protocols Changing between the drivers is easily done trough SM...

Страница 3: ...3 FA 20 Product information...

Страница 4: ...is exceeded these conditions will be transmitted to the main station through an extraordinary data communication programmable Furthermore the FA 20 saves 3 sets of serial readings The latest reading...

Страница 5: ...o of days 24 h 1h logging 31 27 24 22 20 18 The FA 20 is remotely programmed from the main station logging parameters set up and selection of buffers to which data is logged Logging of pulses and seri...

Страница 6: ...a random number of minutes within a time window which is programmable from the IT centre FA 20 also supports dial back at absolute time where it is the main station who chooses the time including date...

Страница 7: ...can preserve its content Log data and for example the latest monthly reading is always stored in the F RAM which does not need a battery to preserve its memory FA 20 features a special integrated cir...

Страница 8: ...4 band GSM module Temperature range 20 to 45 Relative humidity 15 to 95 not condensing Density class IP54 Dimensions 105 x 180 x 50 mm W x H x D without antenna Remember 30 mm clearance for cable entr...

Страница 9: ...ultical 801 via data module an without compatability module KM6 data module is mounted internally in 801 8 Div Multical with M bus module mounted internally in Multical Max M bus 9 Unigas 61E via data...

Страница 10: ...10 FA M2000 GSM main station modem...

Страница 11: ...s ready for use and special settings of parameters can be installed and stored permanently in the GSM modems memory FA M2000 supports V 110 data communications which allow data to be transferred at sp...

Страница 12: ...12 Installation guide FA 20...

Страница 13: ...n the lid is pulled downwards until it locks 2 The physical location of FA 20 Typically FA 20 is placed next to one of the meters that are to be logged The most convenient location is against a wall v...

Страница 14: ...y sending FA 20 a SMS FA 20 with firmware 1 30 or later contains as minimum the following software drivers KMX handles various Multical with 3 wire data module i e Multical III 66C Compact 401 and 601...

Страница 15: ...to terminal 10 in FA 20 Brown wire Reg pin 5 in Unigas is connected to terminal 11 in FA 20 It is recommended to connect FA 20 directly to the internal plug in Unigas and let the plug with the RPG co...

Страница 16: ...with M bus L G WSD and WSF L G 2WR4 2WR5 and UH50 with G2 or G4 Sensus Mechanical water meter with M bus Hydrometer Sharkey with M bus and Infocal 5 with M bus ABB Type Delta with M bus Use Fa 20 conn...

Страница 17: ...n communication with the GSM GPRS modem the big red LED Top right corner visible through the lid will after a few seconds flash quickly and stable to indicate errors Common log operation is stopped 9...

Страница 18: ...will light constantly during the communication and in case of error the red LED will report the error by a 3 second long flash Note Automatic readout after power up Approximately 2 3 min after power...

Страница 19: ...ed LED is ON for 3 sec Failure without any permanent influence on normal operation 1 A serial reading of a meter failed 2 Data communication with the main station failed 3 Brief power failure More aty...

Страница 20: ...If there is no power error like in point 1 and the little green internal LED is turned off then it is properly an error in the GSM modem and the FA 20 should be taken down and sent to service If the...

Страница 21: ...eadout from serial meters then you can test the communication between the FA 20 and serial meters by pushing the key After a keystroke the big green LED will flash once briefly per second by readout o...

Страница 22: ...002000 Pulse counter stand for pulse input no 2 In 1 OFF 2 OFF Signal on digital input no 1 on off and no 2 on off In 3 OFF 4 OFF Signal on digital input no 3 on off and no 4 on off Out 1 OFF 2 OFF Re...

Страница 23: ...nd for M1 Volume 839 Volume counter stand for M1 Mbus2 90012312 Serial no read from meter connected to M2 Energy 3552 25 Energy counter stand for M2 Volume 88243 88 Volume counter stand for M2 Multi 3...

Страница 24: ...variants Above is the fully wired version with 4 pulses or digital S01 inputs 2 relay outputs and 2 x 0 4 20 mA inputs Below is a variant only with 4 pulses or digital inputs Relay outputs Max 27Vdc...

Страница 25: ...Ds in the middle column shows pulses from pulse input 5 to 8 and the orange LEDs in the right column shows pulse inp Pulse input 9 to 12 in connector In the middle to the right NOTE Pulse input 1 and...

Страница 26: ...cates the current status of the output Light in the LED means output is active closed loop Specification These are 2 electrically isolated optocoupler outputs Max applied voltage is 27Vdc open loop Ma...