PRE-START-UP CHECKLIST
Pre-Start-Up Checklist must be completed by installing contractor and submitted to the Carrier start-up team
or the start-up contractor.
PROJECT INFORMATION
Project Name_______________________________________
Address __________________________________________
City_______________________________________________
State/Providence________________ Zip Code ____________
Installer ___________________________________________
Contact Name______________________________________
Contact Phone______________________________________
Contact Email_______________________________________
UNIT INFORMATION
Model Number__________________________________Serial
Number ___________________________________________
INSTRUCTIONS
Check the box to verify the activity has been completed. If the activity does not apply, write N/A in the box.
Refer to the unit submittal for airflow, static, and leaving air temperature conditions.
Installation
All packing materials have been removed from the unit.
The unit is free of damage. If damage exists, contact your local Carrier representative.
The unit has been installed in accordance with required service clearances and required access.
The unit is within level tolerances to promote proper condensate drainage.
All required field installed unit components (hoods, filters, sensors, etc.) have been installed.
Space cooling and heating units exist to control space conditions (temperature and humidity).
Electrical
The unit power feed is installed.
The unit voltage and frequency have been verified to match the incoming power and phasing.
The power feed phasing is correct.
The power feed meets the MCA requirements as indicated on the unit label.
The fuses or circuit breaker safeties meet the MOCP requirements as indicated on the unit label.
All electrical connections and terminals are tight; all terminals are free from corrosion.
Supply Fan
The supply fan(s) are free from obstruction and rotate properly.
The design supply fan airflow is _________ CFM.
The supply fan will be controlled by (circle one): constant speed / duct pressure / space pressure / airflow station.
For duct pressure control, the design duct static pressure is _________ in. wg
For space pressure control, the design building static pressure is _________ in. wg
The outdoor air screens are installed and are clean.
The evaporator filters are installed and are clean.
Filter Status Switch (in filter section)
Verify that the adjustment screw on the front of the switch is fully clockwise (do not strip threads).
Cooling
The air-cooled condenser coil(s) is clean and free from obstructions and defects.
The evaporator coils are clean and free from obstructions and defects.
The refrigeration circuit is free from leaks.
The condensate drain trap has been installed per installation instructions and is draining freely.
The crank case heaters verified to be operational and will operate 24 hours prior to cooling start-up.
Cooling mode will be enabled by (circle one): OAE / OAT / OAT & OADP / OAT & OAE / OAT vs. SAT.
The cooling circuit 1 should be enabled above: _________
The design cooling coil leaving air temperature is: _________ (default is 55°F).
The design cooling supply air temperature (SAT) is: _________ (default is 70°F).
For dual circuit units, the cooling circuit 2 should be enabled above: _________