VIII. Initial Installation Data 

 

The following initial installation data should be maintained on site: 
 

 

Date and Initial open circuit voltage of unit(s) at time of delivery to the site. 

 

Freshening charge records, if performed. 

 

Initial torque value used for connections. 

 

Overall system float voltage across battery terminals. 

 

Individual unit float voltage. 

 

Internal Ohmic value of each unit. 

 

Connection resistances.  

 

Float current. 

 

 

 

 

IX. Periodic Maintenance 

These VRLA batteries are maintenance free with respect to the electrolyte. However, the charging voltage, 
temperature, performance and connection resistances must be periodically monitored and any necessary 
corrective actions taken if irregular values are observed to assure reliable standby power when required.  

 

Quarterly Inspection 

 

Measure and record the system total float charging voltage at the battery terminals  

 

Record the charger on charge output current and voltage  

 

Record the ambient temperature and condition of ventilation equipment 

 

Visually inspect the batteries and rack for general appearance, cleanliness or any irregularity. 

 

If gas tubing provisions are utilized, check for any obstructions in the tubing which would prevent 
the free flow of gases thru the exit point. 

 

 

 

 

 

Semiannual Inspection  

 

Repeat the quarterly checks  

 

Record the on charge voltage of each unit 

 

Optionally perform and record Ohmic checks for trending purposes 

 

Yearly and Initial Inspection  

 

Repeat the semiannual checks 

 

Inspect all connections to ensure integrity.  

 
 
 
 
 
 
 
 
 

Any data, descriptions or specifications presented herein are subject to revision by  
C&D Technologies, Inc. without notice. While such information is believed to be accurate 
as indicated herein, C&D Technologies, Inc. makes no warranty and hereby disclaims all 
warranties, express or implied, with regard to the accuracy or completeness of  such 
information. Further, because the product(s) featured herein may be used under 
conditions beyond its control,  C&D Technologies, Inc. hereby disclaims all warranties, 
either express or implied, concerning the fitness or suitability of  such product(s) for any 
particular use or in any specific application or arising from any course of dealing or usage 
of trade. The user is solely responsible for determining the suitability of the product(s) 
featured herein for user’s intended  purpose and in user’s specific application.  
Copyright 2014   C&D TECHNOLOGIES, INC.    Printed in U.S.A.    RS-2046   0514/CD

 

1400 Union Meeting Road 
P.O. Box 3053 • Blue Bell, PA 19422-0858 
(215) 619-2700 • Fax (215) 619-7899 • (800) 543-8630 
[email protected] 

www.cdtechno.com

 

 

 

Содержание TEL12-105FNSG

Страница 1: ...rmation www cdtechno com Technical Warranty Assistance contact C D Technologies Inc 1400 Union Meeting Road PO Box 3053 Blue Bell PA 19422 0858 800 543 8630 or 215 619 2700 Fax 215 619 7899 Before han...

Страница 2: ...TEL12 170F FG 1 15028593 8mm x 16 1 15028594 2 15028591 15028595 15028596 1 15028538 TEL12 180F 1 30046800 20 x 3 4 1 15029218 2 15029217 N A N A 1 15028506 TEL12 190F FG 1 15028593 8mm x 16 1 1 15028...

Страница 3: ...trolyte which contains dilute sulfuric acid this is harmful to the skin and eyes is electrically conductive and is corrosive If electrolyte contacts the skin wash immediately and thoroughly If electro...

Страница 4: ...ohm meter ohmic test set 100 amp momentary load test set or system load bank Typically for Telecom applications four individual batteries are connected in series to form a higher voltage string of ba...

Страница 5: ...e terminal to battery 2 s positive terminal as shown in Figure 4 Tighten bolt washer assembly hand tight Step 5 Repeat using the provided inter unit bus bar and hardware bolt and washer connect betwee...

Страница 6: ...gative terminal to String A battery 2 s positive terminal as shown in Figure 5 Tighten bolt washer assembly hand tight Step 6 Torque each of the above bolt washer assemblies as per the inch pound spec...

Страница 7: ...unsafe condition VI Freshening Charge When the batteries have been in storage or transit for an extended period over 6 months or if OCV s are below 12 48 volts or when the number of cells in series i...

Страница 8: ...vent the free flow of gases thru the exit point Semiannual Inspection Repeat the quarterly checks Record the on charge voltage of each unit Optionally perform and record Ohmic checks for trending purp...

Отзывы: