Series -48VDC connection of individual front access batteries 

 

Step 1.

  

If installing in a multiple tier rack or cabinet arrangement, always begin with the lowest shelf, 

string A, place each the individual front access batteries on the shelf (typically 4 per level) with 
approximately 1/2 inch spacing between the individual units. All the batteries should be placed with 
terminals to the front of the rack / shelf. Remove and save terminal protectors. 

 
Step 2.   C&D recommends, prior to connection of inter-unit bus bars and lugged cables, the battery 
terminals and all contact surfaces should be neutralized, cleaned, lightly brushed with a brass bristle brush 
or scotch brite type pad and lightly coated with protective No-Ox-Id terminal grease. Use caution to avoid 
fully removing coating and exposing copper insert. 

 

Step 3a. Starting at the battery on the right, which is to be the positive (+) output, label it as number 1 and 
then label the adjacent batteries (right to left) in ascending numerical order 2, 3 & 4. 

 
Step 3b.  If more than one 48 VDC string is within the enclosure, number the additional batteries the same 
way.  Identify the bottom string as string A with the string above if present as string B and soon.  

 
Step 4.  Using the provided inter-unit bus bar and hardware (bolt and washer), connect between battery 1’s 
negative (-) terminal to battery 2’s positive (+) terminal as shown in Figure 4.  Tighten bolt washer assembly 
hand tight. 

 
Step 5.  Repeat, using the provided inter-unit bus bar and hardware (bolt and washer), connect between battery 
2’s negative (-) terminal to battery 3’s positive (+) terminal. Tighten bolt washer assembly hand tight. 

 
Step 6.  Repeat, using the provided inter-unit bus bar and hardware (bolt and washer), connect between battery 
3’s negative (-) terminal to battery 4’s positive (+) terminal.  Tighten bolt washer assembly hand tight.   

 
Step 7.  Torque each of the above bolt washer assemblies as per the inch-pound specifications in Table 3 for the 
appropriate product.    

 
Step 8.  Following the rack or cabinet manufacturers cabling guidelines attach the lugged power lead connections  
to positive (+) of battery 1 and negative (-) battery 4 terminals verifying proper polarities are observed. 

 
Step 9.  Torque all remaining bolt washer assemblies as per the inch-pound specifications in Table 3 for the 
appropriate product.    

 
Step 10.  Repeat for additional battery string if multiple strings are present. 

 
Step 11.  Install all protective terminal covers and use a utility knife or diagonal cutter to trim the cover as 
needed allowing for proper cable routing.  

 
Step 12.  Verify charging equipment is set for proper float voltage of 2.25 to 2.30 volt per cell at 77°F at the 
battery terminals (54 to 55.2Vdc for a nominal 48 volt battery). 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 5 – 24 volt string configuration (typical) 2 strings to be in parallel shown

 

 

 

RS02046/0514/CD 

 

 

 

 

 

 

 

www.cdtechno.com 

Содержание TEL12-105FNSG

Страница 1: ...rmation www cdtechno com Technical Warranty Assistance contact C D Technologies Inc 1400 Union Meeting Road PO Box 3053 Blue Bell PA 19422 0858 800 543 8630 or 215 619 2700 Fax 215 619 7899 Before han...

Страница 2: ...TEL12 170F FG 1 15028593 8mm x 16 1 15028594 2 15028591 15028595 15028596 1 15028538 TEL12 180F 1 30046800 20 x 3 4 1 15029218 2 15029217 N A N A 1 15028506 TEL12 190F FG 1 15028593 8mm x 16 1 1 15028...

Страница 3: ...trolyte which contains dilute sulfuric acid this is harmful to the skin and eyes is electrically conductive and is corrosive If electrolyte contacts the skin wash immediately and thoroughly If electro...

Страница 4: ...ohm meter ohmic test set 100 amp momentary load test set or system load bank Typically for Telecom applications four individual batteries are connected in series to form a higher voltage string of ba...

Страница 5: ...e terminal to battery 2 s positive terminal as shown in Figure 4 Tighten bolt washer assembly hand tight Step 5 Repeat using the provided inter unit bus bar and hardware bolt and washer connect betwee...

Страница 6: ...gative terminal to String A battery 2 s positive terminal as shown in Figure 5 Tighten bolt washer assembly hand tight Step 6 Torque each of the above bolt washer assemblies as per the inch pound spec...

Страница 7: ...unsafe condition VI Freshening Charge When the batteries have been in storage or transit for an extended period over 6 months or if OCV s are below 12 48 volts or when the number of cells in series i...

Страница 8: ...vent the free flow of gases thru the exit point Semiannual Inspection Repeat the quarterly checks Record the on charge voltage of each unit Optionally perform and record Ohmic checks for trending purp...

Отзывы: