Figure A
Wedge Anchor
1/2"
1. Lay out a concrete pad. Requires a minimum of 21"(length) x 24"(width) x 24"(20" depth below
ground, 4" above ground). See Step 1 for the position of the concrete pad.
2. Install the electrical conduit. One conduit is required for a single gate.
For double gates, add another conduit. For underground loops,
add another conduit.
3. Pour the concrete pad.
4. Use 4 wedge anchors 1/2" to secure the gate operator to the concrete. Figure A
Above Ground 4"
Below Ground
Underground
depth may vary
due to local
building codes.
Reinforced
concrete
recommended.
20"
Conduit
21"
24"
CAUTION
Contact local underground utility locating companies
before digging more than 12 inches deep to avoid
damaging underground power, gas or other utility lines.
21"
Conduits should be 6-12"
apart from one another to
avoid interference.
Step 2: Install a Concrete Pad
Concrete Pad, Top View
9