background image

SATK40 & Procyl

®

2

General Information

Please leave the manual as a reference guide for the user. 

Dispose of any packaging in an appropriate manner, most 
of which can be recycled.

In this Installation, Operation and Maintenance guide we 
have endeavoured to make the information as accurate as 
possible.

We cannot accept any responsibility should it be found 
that in any respect the information is inaccurate or 
incomplete or becomes so as a result of further 
developments or changes to the products. 

Key to Symbols

Safety Instructions

7

In the case of particularly hard or impure water, there must 
be suitable provision for filtering and treating the water 
before it enters the device, in accordance with current 
legislation. Failure to do so may result the HIU becoming 
damaged or working incorrectly.

8

Any use of the HIU other than it’s intended use is prohibited.

9

Any coupling of the device with other system components 
must be made while taking the operational characteristics of
both units into consideration.

10

An incorrect coupling could compromise the operation of 
the device and/or system.

NOTE: Risk of electric shock. Live parts. Shut off the electric 

supply before opening the HIU cover.

1

During installation and maintenance operations, always 
avoid direct contact with live or potentially hazardous parts.

2

The device must not be exposed to water drops or humidity, 
direct sunlight, the elements, heat sources or high intensity 
electromagnetic fields.

This device cannot be used in areas at risk of explosion or 
fire.

3

The device must be connected to an independent bipolar 
switch. If work has to be done on the device, switch off the 
electric supply first. Do not use devices with automatic or 
time reset, or which may be reset accidentally.

4

Use suitable automatic protection devices in compliance 
with current legislation.

5

The device must always be earthed before it is connected to 
the electric supply. If the device has to be removed, always 
disconnect the earth connection after disconnecting the 
electric supply. Check that the earth connection has been 
made to the highest of standards under current legislation.

6

Electrical installation must only be carried out by a qualified 
technician, in accordance with current requirements.

Primary circuit flow

Primary circuit return

Domestic cold water inlet

Low temperature circuit flow

Low temperature circuit return

Cylinder circuit flow

Cylinder circuit return

High temperature circuit flow

High temperature circuit return

Содержание Altecnic SATK40103

Страница 1: ...SATK40 Procyl heat interface unit Installation Operation Maintenance Instructions...

Страница 2: ...tures higher than 50 C may cause severe burns When installing commissioning and maintaining the device take the necessary precautions so that these temperatures will not be hazardous for people Conten...

Страница 3: ...t off the electric supply before opening the HIU cover 1 During installation and maintenance operations always avoid direct contact with live or potentially hazardous parts 2 The device must not be ex...

Страница 4: ...he position of the water pipe connections Check the measurements again before installing pipework and electrical cables Hydraulic connections 1 connection to the pipework from the centralised boiler p...

Страница 5: ...ve earthing system constructed as speci ed in current safety regulations This is a compulsory safety requirement Connection to the main supply The device is supplied with an electric supply cable plug...

Страница 6: ...repeat the lling process if necessary Fitting the cover Place the casing over the frame inserting the upper tabs 1 into the corresponding slots 2 Place the lower part of the casing over the frame Tig...

Страница 7: ...circuit pressure switch fault Error code 4 The SATK40 HIU continuously monitors the pressure in the apartments secondary heating circuit If the pressure falls in this circuit the pressure switch is a...

Страница 8: ...power failure the thermal safety valve prevents hot water for heating purposes from entering the system After the user has reset the isolation imposed by the safety thermostat the shut off valve can...

Страница 9: ...e setting 25 to 45 C MEDIUM HIGH temperature setting 50 to 75 C Optional functions Heating cycle modulating temperature regulation with compensated set point floor slab heating function Factory settin...

Страница 10: ...is requested by the room thermostat the circulation pump is powered while the modulating valve is opened gradually until the set point temperature is reached At the end of the heating cycle the circu...

Страница 11: ...etter ef ciency and helps to save energy Before carrying out any maintenance repair or part replacement work proceed as follows Switch off the electric supply Remove the cover Close the shut off valve...

Страница 12: ...cting the connector see page 16 Unscrew the probe Fit the new probe Reconnect the connector respecting the only possible way it can be inserted Expansion vessel pre charge check For the system to work...

Страница 13: ...lay Fused Switch 21 22 6 7 10 11 1 2 3 4 2 5 Com N SL L N E HW On 1 2 3 8 4 CH On 8 9 9 2 10 11 1 2 3 L N E Wiring Centre 7 8 9 10 11 1 2 3 4 5 6 5 2 6 7 L N Br Bl Gr Or Not supplied wiring to be made...

Страница 14: ...i ed personnel to have it replaced electronic controller not working call quali ed personnel to have it replaced all LEDs are off electricity power supply switched off switch on electricity supply pro...

Страница 15: ...faulty call quali ed personnel to have it replaced presence of air in the system vent the system pump not working call quali ed personnel to have it replaced pump cable not connected restore connecti...

Страница 16: ...ecnic co uk IOM 033 23 10 15 E O E Notes In these Installation Operation and Maintenance Instructions we have endeavoured to make the information as accurate as possible We cannot accept any responsib...

Отзывы: