background image

SATK40 & Procyl

®

10

Operating Cycles

Heating cycle

Modulating temperature regulation with compensated set
point - LOW temperature

The function is enabled by setting dip switch 1 to the OFF
position.

When the function is enabled, the flow temperature is modified
according to the temperature detected by the compensation
probe.

This keeps the actual thermal output of the under floor heating
and therefore the ambient thermal load under control. The
thermal response time of the system is thus minimised.

Safety and alarms

Error codes associated with faults signalled by the lighting up of
the FAULT LED are also shown on the display (see page 7).

Operating Cycles

Maintenance

All maintenance procedures should be carried out by an
qualified technician.

Regular maintenance guarantees better efficiency and helps to
save energy.

Before carrying out any maintenance, repair or part
replacement work, proceed as follows:

Switch off the electric supply

Remove the cover

Close the shut-off valves

Empty the HIU using the drain cocks provided.

Heat exchanger replacement

To remove the heat exchanger, loosening the 2 hexagon 
headed screws holding it in place (A)

Replace the heat exchanger and the O-rings.

Refit and tighten the two fixing screws (A) with a maximum 
torque of 3.5 N/m.

N.B. The pins fixing the heat exchanger are positioned in such a
way as to allow it to be placed only in the correct direction.

Maintenance

Cleaning the strainer element

The HIU has a strainer on the flow (inlet) from the centralised
boiler plant and on return from the heating circuit.

To clean these strainers, carry out the following maintenance
procedure:

Unscrew the cap (B)

Remove the strainer mesh and discard any impurities

Put the strainer mesh back in

Screw the cap back on.

B

A

A

1

OFF

60

4

Содержание Altecnic SATK40103

Страница 1: ...SATK40 Procyl heat interface unit Installation Operation Maintenance Instructions...

Страница 2: ...tures higher than 50 C may cause severe burns When installing commissioning and maintaining the device take the necessary precautions so that these temperatures will not be hazardous for people Conten...

Страница 3: ...t off the electric supply before opening the HIU cover 1 During installation and maintenance operations always avoid direct contact with live or potentially hazardous parts 2 The device must not be ex...

Страница 4: ...he position of the water pipe connections Check the measurements again before installing pipework and electrical cables Hydraulic connections 1 connection to the pipework from the centralised boiler p...

Страница 5: ...ve earthing system constructed as speci ed in current safety regulations This is a compulsory safety requirement Connection to the main supply The device is supplied with an electric supply cable plug...

Страница 6: ...repeat the lling process if necessary Fitting the cover Place the casing over the frame inserting the upper tabs 1 into the corresponding slots 2 Place the lower part of the casing over the frame Tig...

Страница 7: ...circuit pressure switch fault Error code 4 The SATK40 HIU continuously monitors the pressure in the apartments secondary heating circuit If the pressure falls in this circuit the pressure switch is a...

Страница 8: ...power failure the thermal safety valve prevents hot water for heating purposes from entering the system After the user has reset the isolation imposed by the safety thermostat the shut off valve can...

Страница 9: ...e setting 25 to 45 C MEDIUM HIGH temperature setting 50 to 75 C Optional functions Heating cycle modulating temperature regulation with compensated set point floor slab heating function Factory settin...

Страница 10: ...is requested by the room thermostat the circulation pump is powered while the modulating valve is opened gradually until the set point temperature is reached At the end of the heating cycle the circu...

Страница 11: ...etter ef ciency and helps to save energy Before carrying out any maintenance repair or part replacement work proceed as follows Switch off the electric supply Remove the cover Close the shut off valve...

Страница 12: ...cting the connector see page 16 Unscrew the probe Fit the new probe Reconnect the connector respecting the only possible way it can be inserted Expansion vessel pre charge check For the system to work...

Страница 13: ...lay Fused Switch 21 22 6 7 10 11 1 2 3 4 2 5 Com N SL L N E HW On 1 2 3 8 4 CH On 8 9 9 2 10 11 1 2 3 L N E Wiring Centre 7 8 9 10 11 1 2 3 4 5 6 5 2 6 7 L N Br Bl Gr Or Not supplied wiring to be made...

Страница 14: ...i ed personnel to have it replaced electronic controller not working call quali ed personnel to have it replaced all LEDs are off electricity power supply switched off switch on electricity supply pro...

Страница 15: ...faulty call quali ed personnel to have it replaced presence of air in the system vent the system pump not working call quali ed personnel to have it replaced pump cable not connected restore connecti...

Страница 16: ...ecnic co uk IOM 033 23 10 15 E O E Notes In these Installation Operation and Maintenance Instructions we have endeavoured to make the information as accurate as possible We cannot accept any responsib...

Отзывы: