Commissioning the heating system
Logano plus GB402 - Subject to technical modifications!
37
7.16
Installing casing parts
B
Hook in the rear side panels first at the bottom
(excluding insulation) [3], then raise slightly and hook in
at the top.
B
Using locking screws, secure the rear side panels to
the boiler back panel [3].
B
Hook in the front side panels first at the bottom
(including insulation) [2], then raise slightly and hook in
at the top.
B
Using locking screws, secure the front side panels at
the front [2] of the boiler.
B
First hook in the bottom of the front panel [1], then raise
slightly and hook in at the top.
B
With locking screws, secure the top of the front panel
[1] to the boiler.
B
Affix the clear pocket containing the technical
documentation in a clearly visible spot on the side of
the boiler.
Fig. 37 Installing casing parts
1
Front
2
Front side panels (incl. thermal insulation)
3
Rear side panels (excl. thermal insulation)
7.17
Informing the owner/operator
and handing over technical
documentation
B
Familiarise the owner/operator with the entire heating
system and the operating instructions for the boiler.
B
Together with the owner/operator, carry out a
shutdown and restart.
B
Explain to the customer what to do in an emergency,
e.g. a fire, referring to the operating instructions.
B
Hand over the technical documentation to the owner/
operator, and together sign the commissioning report
(
Æ
Chapter 7.18).