Boiler block assembly
8
Logano GE515 - We reserve the right to make any changes due to technical modifications.
33
8.8.4 Hot gas check plate on the front section
At the factory, the hot gas check plates (Fig. 33,
[1]
and
[2]
) are secured to the front section with one Allen screw
each.
8.8.5 Insert the hot gas baffle plates
z
Remove the hot gas baffle plates from the fitting crate
and insert it into the hot gas ways according to the
instructions cast into the body (
Æ
Fig. 34 and the
following table).
Fig. 33 Location of the hot gas check plates
2
1
USER NOTE
The hot gas baffles are already fitted if the
boiler is supplied as pre-assembled unit.
z
You need only remove the corrugated
cardboard packaging used to secure
the baffles in transit.
Fig. 34 Hot gas baffle plates
1
Hot gas baffle plates (unten rechts)
2
Hot gas baffle plates (unten links)
3
Hot gas baffle plates (oben links)
4
Hot gas baffle plates (oben rechts)
3
4
2
1
Boiler
size
Number
of boiler
sections
Length of the
hot gas baffle
plate
in mm
Fitting
instructions on
the hot
gas baffle plate
240
7
680
oben rechts
(r.h. top)
295
8
oben links
(l.h. top)
350
9
unten rechts
(r.h. bottom)
400
10
unten links
(l.h. bottom)
455
11
425
oben rechts
(upper r.h.)
oben links
(top l.h.)
unten rechts
(r.h. bottom)
unten links
(l.h. bottom)
510
12
–
–