7.
53
Parte 7 Arresti
05
-
2015 Rev.1
7.3 PROLONGED SHUTDOWN
For this kind of shutdown, please do as follows:
7.3.a
Move the platform indoor, to an area protected against any
water leakage or condensate; the access to this area must
only be allowed to trustworthy staff (any potential external
tampering condition must be eliminated thus guaranteeing
the operators safety).
7.3.b
Make sure the Platform is in
Zero Power Condition
7.3.c
Perform the ordinary maintenance as described in Part 9
“
Routine Maintenance
”
7.3.d
Clean the machine as descibed in Part 8 Cleaning .
7.3.e
Is preferable remove the Control box as described herunder:
7.3.f
Disconnect the ILME connector and put the safety cover
7.3.g
Remove the Control Box and put it in a safe place.
7.3.h
The Prolonged shutdown procedure is finished.
P6
Q3
Q2
04
-
2020 Rev.01
P
ART 7 SHUTDOWN PHASE