Operation 55/68
RE 15302-WA/05.2019, Hägglunds CB, Installation and maintenance manual ,
Bosch Rexroth Mellansel AB
8.1.2 Start of the hydraulic supply
1.
During initial starting and the period immediately after it, any hydraulic
installation must be regularly and carefully checked at frequent intervals.
2.
The working pressure and charge pressure must be checked to ensure that they
correspond to the contracted values. Check that the charge pressure conforms
to the charge pressure curve, see chapter,
Recommended charge pressure
in data
sheet
RE 15302
.
3. The pressure in the drain line measured at the motor must be less than 3 bar
(43.5 psi). This pressure limit is important for the life of the motor seals.
4.
If leakage occurs, correct the fault and carry out new measurements.
5.
Check all lines, connections, screws, etc. and correct if necessary.
6.
Check other possible leakage points and replace faulty parts.
7.
During the start up period, dirt particles in the system are removed by the filters.
The filter cartridges have to be changed after the first 100 working hours and
after that according to the maintenance chart,
Table 19
. See also Chapter
10.3
(second point) about filter clogged indicators.
It is important that the pressure is limited to 250 bar (3626 psi) when starting up
the motor. This is valid for the first 100 hours.
8.2 Re-commisioning after standstill
For recommisioning, proceed as described in chapter
8.1
.
WARNING
Material or product damage!
Risk of injury or serious injuries.
▶
Before re-commisioning, make sure that the Hägglunds product hasn‘t been
damaged so that the original function changed.
In case of accident or malfunction where it is not possible to determine the status of
the Hägglunds product, please contact your Bosch Rexroth representative.
9 Operation
The product is a component wich requires no settings or changes during operation.
For this reason, this chapter of the manual does not contain any information on
adjustment options. Use the product only within the performance range provided in
the technical data. The machine/system manufacturer is responsible for the proper