Pre-installation
|
19
AU/NZ
6 720 646 195a (2010/11)
3.7
Plumbing manifold
3.7.1
Connections
Use the fittings supplied in the hardware literature pack.
•
If the boiler pipes are to be run behind the boiler
ensure that the pipes pass through the slot in the
white cardboard guide. This is fitted to the frame.
Fig. 16 Pipe dimensions
Fig. 17 Plumbing manifold
WARNING:
If fitting an optional integral
diverter valve.
B
Refer to the “optional integral diverter
valve” installation instructions.
Heating System
¾ inch BSP thread compression
fittings
Gas
¾ inch BSP thread
Tab. 17
Further guidance on pipe routing can be
found printed on the boiler template
(supplied).
1
2
3
4
5
6720646195-07.1W
o
#
Function
From left
case edge
Ø of pipe
connections
1
CH flow
70 mm
¾ BSP
2
Gas
200 mm
¾ BSP
3
CH return
330 mm
¾ BSP
4
Condensate
35 mm
22mm
5
Pressure relief valve
367 mm
½ BSP
Tab. 18 Key to figures 16 & 17
1
2
3
4
5
1
2
3
6720644743-10.1Wo