3 Commissioning
Page
18
of
28
Original installation instructions Hyperion Lithium Ion Energy Storage
3.
Check by pulling the power plugs to make sure that the latching is
engaged.
4.
If there are less than 6 modular batteries: fit the power plugs not
required with the dummy sockets
C
supplied.
5.
Feed the power cables (red and black) as well as PE (yellow-green)
through the left hole in the basic housing and fix them with the
supplied PG screw connection.
NOTE
First lead the cables through the union nut of the PG gland and
then through the outer housing.
6.
Lead the communication cable through the right hole and fix it with the
supplied cable gland.
3.3.3
Closing the housing of the battery system
1.
Position the housing hood (with display) in
front of the housing base and plug the
cable for the display on the board into the
hood.
2.
Insert the hood into the guide at the top
and close it at the bottom with the two
M5x10 screws (4 mm Allen key) which
were unscrewed in 3.2.3.
Figure 6:
Power path
with switching devices
and BMS
Screws M5