Install a 30-1/4" long 2x4 between
the roof sheathing and the soffit
panel
3.
Repeat on opposite side.
1.
Make sure the trusses and gables are plumb.
2.
Refer to the roof sheathing layout. Install
a 48"x59-1/4" sheet at lower front corner.
Sheathing should be flush with soffit and
rest on 1x6 fascia. Secure sheathing with
7d sinkers nails. Space nails 12" apart.
Continue to back gable.
3.
The top row of sheathing will allow a gap
at the top to allow ventilation if ridge vent
is applied. Insert (2) two ply-clips into the
roof sheathing between each truss at the
top row, see drawing on previous page.
flush
Step 21B
Install Roof Sheathing continued
Step 22
Install 2x4s in Front overhang
1.
Starting at the peak install a 77-3/8" long 2x4 between the roof sheathing and the soffit
panels. Set this board flush with edge of soffit panels and roof sheathing. Use 6d galv. nails
on soffit and 7d sinkers through the roof sheathing.
Nail with 7d Sinkers
Nail with 6d Galv.
Air
Space
48"x59-1/4"
OSB
48"x35-1/4"