XPR-10 Series Two-Post Lifts
32
P/N 5900951 — Rev. D — May 2019
Installing the Posts
We strongly recommend having multiple people work together to install the Posts.
⚠
DANGER
Pay
special
attention when installing the Posts. If done incorrectly, the Lift could
fall over, potentially causing damage to the Vehicle, the Lift, and injuring bystanders.
Concrete specifications are:
•
Depth
: 4.25 inches (108 mm) thick
•
PSI
: 3,000 PSI, minimum
•
Cured
: 28 days, minimum
The Concrete floor where you want to install your Lift must meet the following requirements:
•
The floor must be a flat, Concrete floor. It must be level;
do not install the Lift on a surface
with more than three degrees of slope
.
•
Do not install the Lift on cracked or defective Concrete.
•
Check the floor for the possibility of it being a post-tension slab. In this case, contact the building
architect before drilling. Using ground penetrating radar may help you find the tensioned cable.
⚠
WARNING
Cutting through a tensioned cable can result in injury or death. Do not drill into a
post-tension slab unless the building architect confirms you are
not
going to hit a
tensioned cable or you have located it using ground penetrating radar.
If colored
sheath comes up during drilling, stop drilling immediately
.
Anchor Bolt specifications are:
•
Length
: 6.3 inches (160 mm)
•
Diameter
: .75 inch (19 mm)
•
Anchor torque
: 110 – 150 foot pounds
⚠
WARNING
Your Concrete and Anchor Bolts
must
meet these specifications. Only install your
Lift on a Concrete surface. If you install a Lift on asphalt or any other surface, or
your Concrete or Anchor Bolts do not meet these specifications, it could lead to
product damage, Vehicle damage, personal injury, or even loss of life.
BendPak Lifts are supplied with installation instructions and concrete fasteners meeting the criteria as
prescribed by the American National Standard “Automotive Lifts – Safety Requirements for
Construction, Testing, and Validation” ANSI/ALI ALCTV-2006.
⚠
WARNING
Use only the ALI-certified Anchor Bolts that came with your XPR-10 Series Lift. If
you use components from a different source, you void your warranty and
compromise the safety of everyone who installs or uses the Lift.
Lift buyers are responsible for conforming to all regional, structural, and seismic anchoring
requirements specified by any other agencies and/or codes, such as the Uniform Building Code and/or
International Building Code.
Tip
Consider
not
torqueing the Anchor Bolts into position yet. Installing the Overhead
Assembly and doing final leveling may be easier if there is some play in the Posts.
Содержание XPR-10 Series
Страница 9: ...XPR 10 Series Two Post Lifts 9 P N 5900951 Rev D May 2019 Specifications ...
Страница 77: ...XPR 10 Series Two Post Lifts 77 P N 5900951 Rev D May 2019 Labels ...
Страница 78: ...XPR 10 Series Two Post Lifts 78 P N 5900951 Rev D May 2019 ...
Страница 79: ...XPR 10 Series Two Post Lifts 79 P N 5900951 Rev D May 2019 ...
Страница 81: ...XPR 10 Series Two Post Lifts 81 P N 5900951 Rev D May 2019 ...
Страница 82: ...XPR 10 Series Two Post Lifts 82 P N 5900951 Rev D May 2019 ...
Страница 83: ...XPR 10 Series Two Post Lifts 83 P N 5900951 Rev D May 2019 ...
Страница 84: ...XPR 10 Series Two Post Lifts 84 P N 5900951 Rev D May 2019 ...
Страница 85: ...XPR 10 Series Two Post Lifts 85 P N 5900951 Rev D May 2019 ...
Страница 86: ...XPR 10 Series Two Post Lifts 86 P N 5900951 Rev D May 2019 ...
Страница 87: ...XPR 10 Series Two Post Lifts 87 P N 5900951 Rev D May 2019 ...
Страница 88: ...XPR 10 Series Two Post Lifts 88 P N 5900951 Rev D May 2019 ...
Страница 91: ...XPR 10 Series Two Post Lifts 91 P N 5900951 Rev D May 2019 Maintenance Log ...
Страница 92: ...1645 Lemonwood Drive Santa Paula CA 93060 USA 2019 by BendPak Inc All rights reserved bendpak com ...