AIRBLADE® DRYER
Mix and Match
1MANUL011
Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (810) 349-7010 * Fax (810) 380-9681
77
Installation
10-Nozzle Frame Assembly: Floor Mounted
20) Secure the clamp and leg into place on the other side.
Do not tighten the bolts until
the height is set and the frame has been leveled
.
Note:
Drip space is the distance between the last Rinse Arch and the Dryer. Typically, the larger
the drip space, the better the Dryer can perform.
21) Once both legs have been attached to the head beam, space them as shown in the
image below.
Note:
45” dimension is taken from the outside of the driver side leg to the inside of the passenger
side Guide Rail. Actual tunnel depth will vary according to available building space.
22) Once the component is properly placed, leveled in all directions and the legs are
squared, you can tighten all of the fasteners and lag the frame to the floor.
23) Locate the following parts and the two Air Cannon motor assemblies:
Item
Qty
Clamp Assembly (2)
Mounting Bracket Clamp
1
1/2-13 X 3-1/2” HHCS
2
1/2-13 X 4-1/2” HHCS
2
3/8-16 Regular Nut
8
3/8”
Flat Washer
8
3/8”
Lock Washer
4
3/8-16 x 2” HHCS
4
1/2” Flat Washer
4
1/2” Lock Washer
4
AirBlade® Side Mount Weldment
1
Floor
91”
136”
45”