![Baxi EcoBlue Advance 16 Heat ErP Скачать руководство пользователя страница 39](http://html1.mh-extra.com/html/baxi/ecoblue-advance-16-heat-erp/ecoblue-advance-16-heat-erp_installation-and-service-manual_2711776039.webp)
With any other appliances & pilot lights turned OFF the gas rate can be measured. It should be as shown in
Section 3.1
Technical Data.
4.
For IE, it is necessary to complete a "Declaration of Conformity" to indicate compliance with I.S. 813. An example of this is given in I.S. 813 "Domestic Gas Installations".
This is in addition to the Benchmark Commissioning Checklist.
5.
Fig. 41
Working Gas Pressures
If the pressure drops are greater than shown above a problem with the pipework or connections is indicated. Permissible pressure drop across system pipework < 1 mbar.
page 45
7.6 Final Instructions
Carefully read and complete all sections of the
Benchmark Commissioning Checklist
at the rear of this publication that are relevant to the boiler and installation. These
details will be required in the event of any warranty work.
1.
The publication must be handed to the user for safe keeping and each subsequent regular service visit recorded.
2.
Hand over the Users Operating, Installation and Servicing Instructions, giving advice on the necessity of regular servicing.
3.
For IE, it is necessary to complete a "Declaration of Conformity" to indicate compliance with I.S. 813. An example of this is given in I.S. 813 "Domestic Gas Installations".
This is in addition to the
Benchmark Commissioning Checklist
.
4.
Instruct the user in the operation of the boiler controls. Hand over the Users Operating, Installation and Servicing Instructions, giving advice on the necessity of regular
servicing.
5.
Demonstrate to the user the action required if a gas leak occurs or is suspected. Show them how to turn off the gas supply at the meter control, and advise them not to
operate electric light or power switched, and to ventilate the property.
6.
Show the user the location of the system control isolation switch, and demonstrate its operation.
7.
Advise the user that they may observe a plume of vapour from the flue terminal, and that it is part of the normal operation of the boiler.
8.
Complete the label supplied with the inhibitor and stick to the inside of the boiler case. Detail of system treatment must be recorded in the
Benchmark Commissioning
Checklist
.
9.
Baxi EcoBlue Advance 13, 16, 19, 25, 30 Heat ErP Installation Manual
http://interpart.partsarena.eu/System/DATA/Dx/DS1/installation/S219/...
39 of 55