Fig. 35a
Fig. 36
page 38
Undo the screws securing the rear flue blanking plate. Firmly grip the central spigot and pull the plate off the boiler. Ensure that the flue connection seals remain in place
(
Fig. 37
).
9.
Lift the boiler and locate the slots in the wall bracket over the horizontal tongues on the wall bracket. As the boiler is pushed back the wall plate spring latch will positively
engage over the wall mounted bracket (
Figs. AA, BB & CC
).
10.
Locate the slots in the safety bracket over the two vertical tongues on the wall bracket and secure with the two screws (
Fig 38
). Adjust the jack screw to ensure the boiler is
fully vertical and then insert the lower securing screw.
11.
If required fit the trim supplied over the flue terminal or "make good" with sealant or cement.
12.
Ensure that the terminal is positioned with the slots to the bottom (
Fig. 31
). Secure the flue to the elbow with the screws supplied (
Fig. 30
).
13.
It is essential that the flue terminal is fitted as shown to ensure correct boiler operation and prevent water entering the flue.
There must be no part of the air duct (white tube) visible outside the property after installation.
Make good between the wall and air duct outside the building, appropriate to the wall construction and fire rating.
14.
If necessary fit a terminal guard (see
Section 5.3.10
).
15.
If not already done so, make the water connections, fill the condensate trap, connect the condensate drain and connect the gas supply as described in
Sections 5.4.3
,
5.4.4
,
5.4.5
&
5.4.6
respectively.
Fig.37
Baxi EcoBlue Advance 13, 16, 19, 25, 30 Heat ErP Installation Manual