background image

.

Manually move valve in direction CLOSE (figure L-7)
while observing cam for limit switch LSO (figure L-8).
Check overrun and setting of the limit switches as described for end posi-
tion CLOSED.

If no other options (clauses 13. to 15.) require setting:

.

Close switch compartment (see page 24, clause 16.).

19

Multi-turn actuators SAI 6 – SAI 100 / SARI 6 – SARI 100

Operation instructions

for valve automation Inside Containment in nuclear power plants

90°

Figure L-6: Limit switch (LSC)

in end position CLOSED

LSC

Cam

90°

Figure L-8: Move limit switch (LSO)

in end position OPEN

LSO

Cam

OPEN

Figure L-7

Move valve in direction
OPEN

CLOSED

Figure L-5:

Move valve in direction
CLOSE

Содержание SAI 100

Страница 1: ...Electric multi turn actuators Operation instructions for valve automation Inside Containment in nuclear power plants SAI 6 SAI 100 SARI 6 SARI 100...

Страница 2: ...tting the limit switching 14 9 1 Setting end position CLOSED 14 9 2 Setting end position OPEN 14 10 Setting the DUO limit switching option 15 10 1 Setting direction CLOSE 15 10 2 Setting direction OPE...

Страница 3: ...g 28 21 Service and training 28 22 Spare parts list actuators SAI SARI 6 SAI SARI 100 30 22 1 Electrical connection with terminals 32 22 2 Electrical connection with AUMA plug socket connector 33 22 3...

Страница 4: ...Non observance of the warnings and notes may lead to serious injuries or damage Qualified personnel must be thoroughly familiar with all warnings and notes in these operation instructions Correct tra...

Страница 5: ...ndwheel reduction via bevel gearbox Electrical connection Standard Terminals Options AUMA plug socket connector Line bushings qualified for DBE conditions lengthwise lead seals Threads for cable gland...

Страница 6: ...peration instructions Other information EU Directives Electromagnetic Compatibility EMC 2004 108 EC Low Voltage Directive 2006 95 EC Machinery Directive 2006 42 EC Reference documents Product descript...

Страница 7: ...ing consists of environmentally friendly materials which can easily be separated and recycled We use the following packaging materials wood cardboard paper and PE foil For the disposal of the packagin...

Страница 8: ...b screw 44 01 Completely unfasten bearing lock nut 4 13 with pin wrench Remove stem nut 4 12 together with the upper needle bearing 44 03 and the bearing races 44 04 Protect the removed needle bearing...

Страница 9: ...n Push down change over lever as indicated by the arrow figure C n a n man a operation ere tor e pre ent at t e o tp t r e e t t r e n e er t n e e en t r e s pp e t t e tp t r e e st t r e ter tr pp...

Страница 10: ...emove socket carrier 2 from plug cover 1 Insert cable glands suitable for connecting cables The enclosure protection stated on the name plate is only ensured if suit able cable glands are used Only ca...

Страница 11: ...ls Technical data Power terminals Protective earth Control terminals Terminals max 3 1 50 Description U1 V1 W1 1 to 50 Connecting voltage max 750 V 250 V Type of customer connection Screws Screws Scre...

Страница 12: ...of non acidic grease e g Vaseline to the sealing faces Replace terminal cover or plug cover and fasten bolts evenly crosswise Fasten cable glands with the specified torque to ensure the required enclo...

Страница 13: ...supervision of such an electrician and in accordance with the applicable electrical engineering rules 8 1 Removing the cover from the switch compartment Remove bolts and take off the cover at the swi...

Страница 14: ...handwheel counterclockwise until valve is open then turn back by approximately a turn Push the stud figure J 1 inwards using a screwdriver and turn it The stud remains in this position Slowly turn se...

Страница 15: ...into its original position by spring action LSC Limit switch clockwise closing LSO Limit switch counterclockwise closing LSA Limit switch DUO clockwise rotation LSB Limit switch DUO counterclockwise r...

Страница 16: ...s on the dial indicate the values in mkp 1 mkp 10 Nm 1 lbsft 1 36 Nm Example Setting in figure S 12 mkp 120 Nm Tighten lock screw O again The torque switches can also be operated in manual operation T...

Страница 17: ...urns counterclockwise the direction of rotation is correct If the direction of rotation is wrong switch off immediately Then correct phase sequence at the motor connection and repeat test run 12 2 Che...

Страница 18: ...amount of additional rotation of stem after actuator has been switched off Manually move valve in direction CLOSE figure L 5 while observing cam for limit switch LSC figure L 4 For limit seating in d...

Страница 19: ...require setting Close switch compartment see page 24 clause 16 19 Multi turn actuators SAI 6 SAI 100 SARI 6 SARI 100 Operation instructions for valve automation Inside Containment in nuclear power pl...

Страница 20: ...reduction gearings for the position transmitter the complete resistance range is not always utilized for the whole travel Therefore an external possi bility for adjustment setting potentiometer must b...

Страница 21: ...if necessary 21 Multi turn actuators SAI 6 SAI 100 SARI 6 SARI 100 Operation instructions for valve automation Inside Containment in nuclear power plants Terminal plan KSA _ _ _ Output current Ia 0 2...

Страница 22: ...urrent starts to increase Turn back potentiometer P1 until the following value has been reached for 3 or 4 wire system approx 0 1 mA for 2 wire system approx 4 1 mA This ensures that the signal does n...

Страница 23: ...Turn back potentiometer P1 until a residual current of approx 0 1 mA has been reached Move valve to end position OPEN Set potentiometer P2 to end value 16 mA Move valve to end position CLOSED Set pot...

Страница 24: ...ent with the mark on the cover Indicator disc rotates approximately 270 at full travel from OPEN to CLOSED or vice versa 16 Closing the switch compartment Clean sealing faces of housing and cover Chec...

Страница 25: ...g for tightness in the factory Cable glands For the entries of the motor and control cables appropriate cable glands in enclosure protection IP 68 must be used The size of the cable glands must be sui...

Страница 26: ...ommended that a visual inspection for grease leakage is performed on each actuator at least every 2 years Functional test Every 5 years the performance of each actuator should be tested in detail and...

Страница 27: ...t presse r Fill in new grease respecting correct quantity see table below Replace seals at handwheel Apply grease to lower part of handwheel hub Place handwheel with hub in housing thereby turning it...

Страница 28: ...stances are hazardous to water and must not be released into the environment See disassembled material to a sound disposal or to separate recycling according to materials Observe the national regulati...

Страница 29: ...Notes 29 Multi turn actuators SAI 6 SAI 100 SARI 6 SARI 100 Operation instructions for valve automation Inside Containment in nuclear power plants...

Страница 30: ...n Inside Containment in nuclear power plants Operation instructions Sample name plate Commission number Works number Actuator type Enclosure protection output speed Torque range in CLOSED OPEN Speed o...

Страница 31: ...23 Circlip 024 Circlip 025 Circlip 027 Circlip 030 Hexagon bolt No Designation 031 Hexagon bolt 032 Reduced shaft bolt 033 Oval head screw 034 Hexagon bolt 035 Socket head cap screw 038 Cotter pin 039...

Страница 32: ...017 5 020 5 023 5 025 5 026 5 3 5 03 5 018 5 021 5 024 5 025 5 026 5 01 5 1 5 02 5 2 No Designation 5 1 Terminal frame 5 2 Terminal box cover 5 3 Terminal rails 5 01 O ring 125 X 3 5 5 02 O ring 240 X...

Страница 33: ...valve automation Inside Containment in nuclear power plants No Designation 1 Cover 2 Socket carrier complete 3 Adapter plate 4 Pin carrier 5 Adapter plate 6 Cable harness for protective earth 01 Hexa...

Страница 34: ...nts Operation instructions 28 05 066 028 010 18 29 47 014 064 06 No Designation 18 Bushing 28 Handwheel hub 29 Handwheel 47 O ring retainer 05 O ring for handwheel hub 06 Parallel key No Designation 0...

Страница 35: ...plants No Designation 1 Mounting flange upper part 2 Mounting flange bottom part 3 Hollow shaft 4 Stem nut 5 Bearing lock nut spring loaded in both directions 6 Thrust ring 7 Collar spring loaded in...

Страница 36: ...pare parts list seal kit for actuators SAI SARI 6 SAI SARI 100 36 Multi turn actuators SAI 6 SAI 100 SARI 6 SARI 100 for valve automation Inside Containment in nuclear power plants Operation instructi...

Страница 37: ...g __ 050 52 x 1 78 K000 399 1 069 45 x 3 53 K000 403 1 088 50 x 3 53 K000 407 1 014 Radial seal BABSL 35 x 52 x 6 D000 222 1 __ __ __ __ __ __ 064 1 O ring 56 82 x 2 62 D001 640 1 76 x 2 D000 361 1 10...

Страница 38: ...Declaration of Incorporation and EC Declaration of Conformity 38 Multi turn actuators SAI 6 SAI 100 SARI 6 SARI 100 for valve automation Inside Containment in nuclear power plants Operation instructio...

Страница 39: ...Lubrication 27 M Maintenance 4 Manual operation 9 Mechanical position indicator 24 Motor protection 11 Mounting to valve gearbox 7 N Name plate 30 O Output drive type AF 9 35 Output drive types 7 Ove...

Страница 40: ...ed information about AUMA products refer to the Internet www auma com Y000 580 003 en 2 AUMA Riester GmbH Co KG P O Box 1362 DE 79373 Muellheim Tel 49 7631 809 0 Fax 49 7631 809 1250 info auma com www...

Отзывы: