SECTION V PREVENTIVE MAINTENANCE, CARE AND CLEANING
- 5-4 -
5.2.3
Monitor System Checkout Procedure
The following test procedure should be performed periodically to ensure that the A-2000
is functioning properly.
1. Connect power cable to monitor, plug power connector into appropriate wall outlet.
2. Power up monitor by pressing power button (lower right side of case).
•
Verify beep tone as power switch is activated
•
Verify fan (rear case wall) moves air outward.
•
Verify that all self tests complete successfully (approx. 30 seconds).
•
Verify next screen says ‘CONNECT DSC CABLE TO FRONT OF MONITOR’
3. Connect DSC, with PIC and Sensor. (Refer to Sensor Check, section 5.2.5.).
•
Verify that DSC test completes
•
Verify SENSOR CHECK screen displays.
4. Exit from SENSOR CHECK screen by passing impedance check or by exiting with
MENU/EXIT key.
5. Disconnect power cord.
•
Verify ‘OPERATING ON BATTERY BACKUP (E33)’ is displayed.
•
Verify battery icon displays in BIS banner (top left corner of screen).
6. Reconnect power cord.
•
Verify battery icon is not displayed in BIS banner
•
Verify no ‘OPERATING IN BATTERY BACKUP (E33)’ display.
7. Perform keyboard checkout:
•
Press SILENCE key
Verify icon shows at BIS banner
•
Press Review ARROW BACK key
Verify REVIEW MODE Menu displays
•
Press MENU/EXIT key
Verify REVIEW MODE MENU exits,
•
Press Review ARROW AHEAD key
Verify REVIEW MODE Menu displays
•
Press MENU/EXIT key
Verify REVIEW MODE MENU exits
•
Press MENU/EXIT key
Verify Setup Menu displays
•
Press UP ARROW key
Verify highlight bar moves up with each
press.
•
Press DOWN ARROW key
Verify highlight bar moves down with
each press.
•
Press SELECT key
Verify that highlighted menu line is
selected.
•
Press MENU/EXIT
Verify that Setup Menu exits
8.
End of checkout procedure.
Содержание BISPECTRAL INDEX A-2000
Страница 9: ...SECTION I INTRODUCTION 1 4 Figure 1 1 The A 2000 BIS Monitoring System...
Страница 11: ...SECTION I INTRODUCTION 1 6...
Страница 19: ...SECTION III PRINCIPLES OF OPERATION 3 2 Figure 3 1 The A 2000 System Block Diagram...
Страница 20: ...SECTION III PRINCIPLES OF OPERATION 3 3 Figure 3 2 The A 2000 Signal Flow Diagram...
Страница 35: ...SECTION V PREVENTIVE MAINTENANCE CARE AND CLEANING 5 6...
Страница 53: ...SECTION VI DIAGNOSTICS AND TROUBLESHOOTING 6 18...
Страница 59: ...SECTION VII DISASSEMBLING AND REASSEMBLING THE A 2000 7 6 Flange Figure 7 3 The Keypad Cable Tension Flange...
Страница 61: ...SECTION VII DISASSEMBLING AND REASSEMBLING THE A 2000 7 8 Figure 7 4 The Four Mounting Screws...
Страница 71: ...SECTION VII DISASSEMBLING AND REASSEMBLING THE A 2000 7 18 L bracket Figure 7 15 The L Bracket Installed...
Страница 76: ...SECTION VII DISASSEMBLING AND REASSEMBLING THE A 2000 7 23 Tie Wraps J 300 Figure 7 19 Battery and cable...
Страница 85: ...SECTION VIII A 2000 SPECIFICATIONS 8 4 8 3 Digital Signal Converter DSC Connector LEMO 5 female...
Страница 91: ......