5 INSTALLATION
The installation section is divided into two parts. The first will cover mechanical installation, the
second, electrical installation.
Read this manual thoroughly prior to attempting the installation. Improper installation is the most
significant cause of system start-up problems and service issues over the product’s life. Upon
receipt of the equipment, perform an external visual inspection. Verify that nameplate information
is consistent with the ship’s power requirements (required form, voltage, and frequency).
Proper planning will speed up installation, location, and connection of the equipment. Follow the
suggested minimum clearances provided in Table 2.
Ensure the room/compartment has adequate
ventilation and cooling. The thermal load presented by AC36V will be approximately
10,500BTU/Hr at maximum continuous load, 13,060BTU/Hr for the AC45V, and
15,670BTU/Hr for the AC54V.
THE CONVERTERS ARE HEAVY, WEIGHING UP TO 840lbs DEPENDING
UPON MODEL AND INSTALLED OPTIONS. EXTREME CAUTION MUST
BE EXERCISED IN HANDLING AND INSTALLATION TO AVOID
EQUIPMENT DAMAGE OR INJURY TO PERSONNEL. AN ADEQUATE
MATERIAL HANDLING DEVICE SHOULD BE USED FOR UNLOADING,
MOVING, AND POSITIONING THE SYSTEM.
Содержание AC36V-1
Страница 15: ...AC36V 1 3 AC45V 1 3 AC54V 1 3 Operations Manual 15 5 1 MECHANICAL INSTALLATION cont FIGURE 2 MECHANICAL OUTLINE...
Страница 16: ...AC36V 1 3 AC45V 1 3 AC54V 1 3 Operations Manual 16 5 1 MECHANICAL INSTALLATION cont FIGURE 3 CONTROLS...
Страница 34: ...AC36V 1 3 AC45V 1 3 AC54V 1 3 Operations Manual 34 6 5 REMOTE COMMUNICATIONS cont FIGURE 7 RS 232C PINOUT...
Страница 56: ...AC36V 1 3 AC45V 1 3 AC54V 1 3 Operations Manual 56 8 DIAGNOSTICS cont FIGURE 8 STATUS WORD BIT DEFINITIONS...