Commissioning
26
Gas supply
Check the gas supply connection to
the boiler for tightness. If any leak
-
age is found, reseal the leakage be
-
fore starting the boiler!
Remove any air between the gas
valve and the gas line. This can be
done at the test point (1) at the gas
pressure switch.
Don’t forget to close the test point
afterwards!
Check the gas type and values with
the local gas company, in order to
know for which gas type the boiler
should be commissioned.
Consult the conversion kit instruc
-
tion if the boiler is to be installed
with natural gas L or LPG.
Gas supply
Flue and air intake connections
Condensate connection
Condenstate connection
Fill the syphon as shown on the pic
-
tures with water.
Check the connections, make sure
the syphon is filled and that the
cover of the condens tray is closed
before starting the boiler, in order
to prevent flue gases discharging
through the condensate tray and
syphon!
Flue and air intake connections
Check whether the flue and air in
-
take systems are made according to
the national and local regulations.
Installations which don’t comply
with the regulations, are not al
-
lowed to be commissioned.
Make sure that all connections are
free.
The size of flue gas and air intake
connections may not be reduced.
1
N
Содержание SUPAflo EVO SF60 EVO
Страница 1: ...INSTALLATION AND SERVICE MANUAL SUPAflo EVO Water Heater SF60 EVO...
Страница 2: ......
Страница 15: ...Installation 15 EN Disassemble the casing 7 8 9...
Страница 23: ...Installation 23 EN Wiring diagram Boiler...
Страница 46: ...Note 46 Note...
Страница 47: ...Note 47 EN Note...