Maintenance
Maintenance plan
G51--001EN07
16/18
02--2011
© ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be
relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is
provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is
strictly prohibited.
GRID
Detail of maintenance operations of disconnector, earthing switch and (or)
starting disconnector
(where applicable)
General condition of
equipment
To be dealt with during the foreseen circuit--breaker interventions.
Condition of control
rod system
Inspection of the control rod system will be performed at the same time as the
foreseen circuit--breaker interventions.
Mechanical control
mechaism
Check condition of the mechanical control mechanism -- tightness of seals,
moving parts, protection of the various elements...
Tightening of
mountings
To be dealt with during the foreseen circuit--breaker interventions.
Relay operation
To be dealt with during the foreseen circuit--breaker interventions.
Pole insulating
supports
Check the condition of insulating supports ; these should be free from impact
marks, splintering, cracks, dust deposits, pollution etc...
Clean with a dry rag.
If anomalies are found on pole insulating supports, contact
ALSTOM Grid
S.A. Customer Service
.
Pole contacts
These contacts are inspected with the cover removed, the disconnector de--
energized and earthed ; this state is equallyvalid for the previous inspections.
Measurecontactresistancebetween thedisconnector’s input andoutput ter-
minals to appreciate how the condition of these contacts has evolved.
Inspect silver-plating of contact fingers and tube no patches of copper should
be visible. If this is not the case, contact
ALSTOM Grid S.A. Customer Ser-
vice
.
Operating times
Measure operating times of poles and auxiliary contacts as explained in sec-
tion entitled : “PRE-COMMISSIONING INSPECTIONS AND TESTS”.
If the values found are outside those given in the document “Acceptation Cri-
teria”, contact
ALSTOM Grid S.A. Customer Service
.
Measurement of con-
tact resistance
To be dealt with during the foreseen circuit--breaker interventions.
Replacing the earth-
ing switch
In case of an anomaly following a guaranteed maximum overcurrent, contact:
ALSTOM Grid S.A., Customer Service
, in order to envisage changing the
deteriorated parts.
Overhauling necessitates
de--energizing
the equipment.
Содержание FKG1X
Страница 2: ......
Страница 7: ...GRID High Voltage Switchgear This page is intentionally blank...
Страница 13: ...GRID High Voltage Switchgear This page is intentionally blank...
Страница 17: ...GRID High Voltage Switchgear This page is intentionally blank...
Страница 21: ...GRID High Voltage Switchgear This page is intentionally blank...
Страница 75: ...This page is intentionally blank This page is intentionally blank...
Страница 191: ...GRID ALSTOM Grid SAS 130 rue L on Blum 69611 Villeurbanne France This page is intentionally blank...
Страница 197: ...GRID ALSTOM Grid SAS 130 rue L on Blum 69611 Villeurbanne France This page is intentionally blank...