![Alpha ESS T100 Скачать руководство пользователя страница 27](http://html.mh-extra.com/html/alpha-ess/t100/t100_installation-and-operation-manual_2905584027.webp)
______________________________________________________________________
Alpha ESS Co., Ltd.
Page 27 of 45
Your Smart Energy
5.
Operation
Switch on
Check Before Operation
Before operation please check the equipment according to the following procedures:
If no sign of damage is inspected visually outside the inverter module and all of the battery
switch, PV switch and load switch, diesel engine switch are in the "OFF" position, you will
a. check whether the DC input wiring of the energy storage system and the AC output
wiring are normal and whether the earthing is good;
b. check whether the wire connection polarity is normal;
Power-on Procedures
The system shall be turned on in the correct sequence to avoid any damage.
A. Turn on the plastic case breakers of HV900112 in each cluster respectively.
From left to right: OFF- triggered position
-
ON
Figure 5-1
Plastic circuit breaker in switch-off status
B. Turn on the AC switches of HV900112 in each cluster respectively.
Figure 5-2
AC switch in switch-on status