Commissioning
The sever will recognize the the model according to the SN and the battery model will be required to
input.
5.6
Basic configuration
The installer will choose the work mode and time zone.
5.7
Safety Parameters Settings
Then the grid regulaiton must be chosen and if the safety country is AS4777.2, regional application
standard have to be set for different Volt-Watt & Volt-Var settings. All the country code and regional
application standard are shown in Appendix 2 & 3.
If the enduser want to disable the generation export, set the ‘Max. Feed-in Rated‘ as 0. Or set a feed-
in rate depends.
NOTE: Only the installer and administrator will have the authority to select the safety
country and regional option. The safety country and regional option will be locked after
commissioning unless sending mail to the staff of Alpha ESS.
NOTE: AS4777.2 means the latest standard AS/NZS 4777.2:2020.
5.8
Meter Settings (Optional)