Screw the
body onto
the plastic
core
d. Put the sealing body into the main body groove, and then tighten the lock nut to the main body with
a wrench. Torque 2.0
±
0.3 N
·
m
Put the sealing
body into the
main body and
lock the lock nut
with a wrench
Figure 23 Cable Box Bottom View, Wiring Connectors
Step 13-5:
Connect the Backup and Grid cables in advance according to the connector mode, and
connect them to the Backup and Grid board connectors in turn.
NOTE: Recommended AC circuit breaker rating is 32A.
NOTE: Installer in Australia or New Zealand must install external circuit breaker or switch
for PV, backup and grid side.
NOTE: In Australia and New Zealand, the neutral of backup and grid circuit should be
externally connected on the neutral bar.
NOTE: No external earthing required. After the PE line of AC cables has been grounded,
the whole inverter including the case will be grounded.
Female
Female
Female