background image

19 

SETTING THE CLOSE TIMER 

To adjust the amount of time the close timer will hold the gate open, 
use the lower leftmost trimmer potentiometer next to the relay on the 
controller board.  Review Figure 19, Page 17. 
 
 
Close timer delay is adjustable between 2 and 100 seconds.  Turning 
the potentiometer counterclockwise increases the delay; turning it 
clockwise decreases the delay. 

F I N A L   S E T T I N G   O F   T H E  
O B S T R U C T I O N   D E T E C T I O N  
S E N S I T I V I T Y  

The obstruction detection  sensitivity was preset before turning on the 
main power to prevent the operator from "self-tripping" during testing.  
To set the sensitivity, start the gate in motion and turn the overload 
potentiometer counterclockwise until the OVERLOAD light turns on.  
Then back the potentiometer off 10 degrees in the clockwise direction.   
Review Figure 19, Page 17. 
 
Restart the gate and give the leading edge a firm blow with the heal of 
your palm.  Don't stand directly in the gate's path while testing the 
obstruction sensitivity.  The obstruction detection should respond 
immediately to the blow.  The overload potentiometer must be adjusted 
to the most sensitive setting possible without causing "self-tripping" 
due to the gate's inherent friction or to variations in the track.  Try 
readjusting the potentiometer several times by small increments, testing 
the gate in both directions of travel, until you are satisfied. 

TESTING THE OPERATOR LOCK 

STANDARD LOCK 

The Operator is equipped with an operator locking mechanism.  The 
lock is engaged when the gate is stopped and the lock action light is on.  
When the main power is off, the operator lock remains engaged.  The 
key lock on the side of the operator may be used to disengage the lock 
to allow the gate to be pushed open manually. 

DROP OUT LOCK 

The operator lock is engaged when the gate is stopped and the lock 
action light is on.  When the main power is off, the lock is not 
energized and the gate may be pushed open manually.

 

MAXIMUM RUN TIMER (MRT) 

The control board has a non-adjustable maximum run timer circuit.  
The MRT is preset to approximately 45 seconds maximum run time at 
the factory.  If the operator initiates an OPEN or CLOSE cycle and for 
any reason that cycle is not completed within this time, the MRT will 
immediately stop the gate.  Valid commands received during the cycle, 
such as activation of the SAFETY input or a new input command, will 
automatically reset and restart the MRT.  If the MRT has stopped the 
gate, the operator will respond to a new input command. 
 
 
 

BI-PARTING INSTALLATION FINAL SETTINGS 

 
LIMIT SWITCHES - Push both gates together in the center of the 
driveway to set the closed limits.  Push each gate open an equal amount 
to set the open limits.  After cycling the gates the settings can be fine 

tuned to insure that the gates stop in their open positions at the same 
time. 
 
 
SWITCH SELECTABLE OPTIONS - Make sure the three dip 
switches are set identically on both control boards. 
 
 
CLOSE TIMER - If the close timers are enabled, set the adjustment 
potentiometers to approximately the same position on each control 
board.  Cycle the gates several times making slight adjustments to one 
of the potentiometers until the gates timeout and begin closing at 
exactly the same time. 
 
 
When properly adjusted, the two operators will perform as if they were 
a Master/Slave installation.  If the motor overload circuit in one 
operator should respond to an obstruction not encountered by the other, 
the gates will temporarily get out of sync.  If Switch 1 is in the OFF 
position in both operators, synchronization will be restored after the 
next input command cycle 

 

FUSES 

T h e operator 

uses 

three 

Slo-Blo, 

size 3AG, glass-

b o d y 

fuses.  The fuses 

and their 

respective  ratings 

a

r

e listed 

below: 

 

  

1.

FUSE F1

 - 

3/10 Amp, 250 
Volt. 

2.

 

 

3.

FUSE F2

 - 

1 5 Amp, 

125 

Volt. 

4.

 

 

D

: STARTING THE OPERATOR  

RISK OF ELECTROCUTION 

REPLACING ANY OF THE FUSES WITH A HIGHER-

CURRENT-RATED FUSE OR WITH ANY FOREIGN 

MATTER WILL VOID ALL WARRANTIES ON THE  

OPERATOR CONTROL BOARD. 

  WARNING! 

107034 

Figure 21:  Control Board Fuses 

RISK OF ELECTROCUTION 

TURN OFF THE MAIN POWER SWITCH BEFORE 

REPLACING FUSES. 

  WARNING! 

Содержание HDSLG 1000

Страница 1: ...date of manufacture meets all ANSI UL 325 Safety Requirements for Vehicular gate operators HDSLG 1000 Heavy Duty Vehicular Slide Gate Operator READ THIS MANUAL CAREFULLY BEFORE INSTALLATION OR USE Se...

Страница 2: ...rator Lock 19 Maximum Run Timer 19 Final Setting for Bi Parting Installations 19 Fuses 20 Section E Auxiliary Equipment 20 Section F Safety Guide 21 Operator Exploded View Parts List 23 Technical Spec...

Страница 3: ...LG built in overload detector will activate if there is an abrupt increase in motor current above that normally required to move the gate THE OVERLOAD DETECTION POINT IS AN ADJUSTABLE SETTING THAT MUS...

Страница 4: ...gn to protect system entrapment zones Allstar can provide these products for incorporation in your gate installation CANTILEVERED ROLLER GATES WITH OPEN ROLLERS HAVE THE POTENTIAL HAZARD OF HANDS AND...

Страница 5: ...ct any auxiliary equipment to the operator detectors card readers etc until the gate operator and all its functions are fully tested Only connect one device at a time and ensure its proper function s...

Страница 6: ...ide of the operator Four redhead bolts 3 8 or 1 2 in diameter should be used for mounting the operator The bolt pattern is 10 wide by 16 3 4 long The two rear bolts closest to the gate should be no cl...

Страница 7: ...to determine the correct wire size The NOMINAL column is the ideal distance from the breaker panel to the operator for a given wire size The distances shown in the MAXIMUM column should never be excee...

Страница 8: ...of the slot 8 above the top of the operator pad Attach one end of the chain to the gate and thread the other end through the idler pulleys and drive sprocket Attach the free end to the bracket on the...

Страница 9: ...et failure With the operator properly aligned with the gate drill the remaining three holes with the operator in place Before inserting the remaining redhead bolts make sure the operator is sitting le...

Страница 10: ...lightning strike be shunted to ground This must be done without raising the potential of the circuitry in the operator with respect to ground to the levels that will damage the solid state circuitry L...

Страница 11: ...cturer s instructions Crimp 1 4 quick disconnect lugs to the RELAY COMMON and PRESENCE OUTPUT wires on the detector harness The RELAY COMMON wire is connected to terminal 1 COMMON on the control box 1...

Страница 12: ...ceiver in most cases Many other auxiliary devices such as card readers and key pads using bridge rectifiers require that both sides of the transformer supplying power be floating and not grounded Fail...

Страница 13: ...13 Figure 15 Schematic Wiring Diagram 107788 C INSTALLING THE OPERATOR...

Страница 14: ...vated the gate will not move Gate will move briefly if RADIO or PULSE is activated Gate will run open if HOLD OPEN is activated 7 ALTERNATE Pulsed signal This input is used for COMMAND OPEN COMMAND CL...

Страница 15: ...y connect the receiver For any 4 wire receiver two of the wires will be for power input and two will be for the relay contacts Locate the AUXILIARY Transformer on the Limit Plate Connect the two wires...

Страница 16: ...when more than one COMMON or ground wire is attached between separate operators All accessory equipment should also be wired to the PRIMARY From each of the control inputs with accessory equipment att...

Страница 17: ...TECTION Switch 1 OFF Open Direction The gate will stop move in the close direction for 1 2 second and park Close Direction The gate will stop move in the open direction for 1 2 second and park SWITCH...

Страница 18: ...ed above EXCEPT NOTE that the Open and Close limit switches are REVERSED SETTING THE OBSTRUCTION DETECTION SENSITIVITY T h e operator is equipped with an obstruction detection circuit which will detec...

Страница 19: ...MUM RUN TIMER MRT The control board has a non adjustable maximum run timer circuit The MRT is preset to approximately 45 seconds maximum run time at the factory If the operator initiates an OPEN or CL...

Страница 20: ...close Remove the plate from the loop and observe that the gate closes Some vehicle detectors will tune out a constant obstruction to the loop after 15 to 30 minutes 3 Installing other entry devices Af...

Страница 21: ...n your gate system install the following safety features Electric gate edges Enclosed tracks Vertical guard posts Protective screen mesh Photoelectric sensors Instructional and precautionary signs Cov...

Страница 22: ...be out of reach of the gate so that no one pushing the button or inserting the card is in the path of the gate or moving parts it must also be within INSTALL SAFETY DEVICES In residential application...

Страница 23: ...y Timing Belt 9 54 PD 60 GR 1 ea 20 102832 Cover Control Box HDSLG 1 ea 11 010605 Shaft Lower HDSLG 1 ea 21 102828 Control Box HDSLG 1 ea 12 010198 Bushing Taper Lock 3 4 Bore 1 ea 22 107786 Motor Con...

Страница 24: ...mily home use and two 2 years from the date of purchase for multi family and commercial use To obtain service contact your dealer To obtain service under this warranty the buyer must obtain authorizat...

Отзывы: