System Installation
4200-106
4-1
Revision 3
4.
System Installation
Note
: The UXIM must be installed in a restricted access location.
UXIM installation requires nothing more than standard hand tools, cutters, strippers and screwdrivers. If
the unit is to be wall mounted, a drill will also be required.
The following is a list of the steps required for successful UXIM system installation. Some items may not
apply due to system requirements.
Installation Task
Refer to Section
Verify materials ordered and received
Materials Received List, page 5-1
Items to consider before system installation
System Installation Considerations, page 6-1
Isolate the battery string
Battery String Isolation, page 6-1
Identify cell/monobloc Number 1
Cell Number 1 Identification, page 6-1
Properly install the tab washers
Installation of Tab Washers, page 7-1
Configure the unit
Mount the equipment
Connect the sense lead harnessing
Sense Lead Harness Connection, page 10-1
Connect the fused load lead harnessing
Fused Resistance Load Lead Harness Connection,
page 11-1
Connect the ambient temperature sensor
Charger Cable Resistance Reading Connection, page
12-1
Connect the digital inputs if applicable
Digital Inputs Connection, page 14-1
Connect RS-485 communications if applicable
RS-485 Communication Connection, page 15-1
Connect the fiber optic interface if applicable
Fiber Optic Communication Connection, page 16-1
Connect the Network communications if
applicable
Network Communication Connection, page 17-1
Connect the alarm contacts if applicable
Parameter Alarm Connection, page 18-1
Connect the Hardware alarm contacts if
applicable
Hardware Alarm Connection, page 19-1
Table 1 - Installation Task List