7 - START-UP
PRELIMINARY CHECKS
Checks with machine in OFF, before start-up
.
For details refer to the various chapters in the manual.
√
Preliminary checks
1
Safe access
2
Are the functional spaces being observed
3
Structure integrity
4
Unit in bubble level
5
Unit on vibration isolators
6
Return air filter available (size 200-650 necessary )
7
Presence of anti-intrusion grille against small animals or leaves (option)
8
Air flow: correct return and supply (no bypass)
9
Completed aeraulic system
10
Insulation of supply conduits to room and air exhaust conduits
11
Presence of anti-vibration joints between the conduit and unit (e.g. canvas conduits)
12
Condensate drain with trap - sloping
13
Presence of electric heater (option) - installed correctly
14
Presence of humidifier (option - sizes 200-650 only) - installed correctly
15
Presence of electrostatic filter (option)
16
Visual check of oil / leak presence
17
Electrical connections provided by the customer
18
Earthing connection
19
Power supply cables separated by signal cables