Verification Procedures
7-8
Verification Procedures
Overview of SDN/ACC Installation and System
Communication Verification Procedures
The following overview depicts the recommended order of on-site
customer engineering activities during SDN/ACC component installation.
Refer to the associated section as indicated to perform the detailed
installation procedures and follow the SDN/ACC installation procedures
in the sequence indicated.
1.
Planning and configuration review
2.
Standalone instrument verification and installation
3.
SDN wiring installation
4.
Instrument connection to the SDN
5.
System communication verification
6.
Simple practical checks
Planning and Configuration Review
Make sure all instruments and SDN components of the SDN
communication system have been received and delivered to the
appropriate installation site.
Review SDN system configuration.
Standalone Instrument Verification and Installation
Unpack the instruments at their installation location. Follow the detailed
unpacking instructions supplied with each instrument.
It is recommended that proper operation of the instrument be verified
prior to mounting. Use the performance verification procedures listed in
each product’s service manual, including any self-test procedures, to
properly verify the functional operation of the instrument.
Refer to “SDN Error Messages and Error Codes” on page 3-5 for a listing of
SDN fault messages for instruments not connected to the SDN.
Unpack the ACC and mount it to a 19” rack. Optionally, wall mount it to
the installed plywood panel (refer to “ACC Wall Mounting Procedures and
Power Installation” on page 8-8). Verify the functional operation of the
ACC by plugging it in and checking the LEDs.
Содержание 78581B
Страница 46: ...ACC Maintenance 4 2 ...
Страница 54: ...Installation Responsibilities Customer and Agilent Technologies 6 4 ...
Страница 90: ...Procedures 8 28 ...
Страница 98: ...Contacts 10 6 ...