60
BU-0101704 R3
Figure 55.
Install the Sweep Stop
4
1
5
6
7
3
3. Measure 3–1/8" (79mm) from the top of the sweep stop to mark and drill a 9/16" hole. Install the hydraulic
fitting and 9/16" jam nut.
4. Run one end of the cable through the top hole on the sweep stop , create a loop and secure with a cable
clamp.
5. Route the other end of the cable through the hydraulic fitting in the bin wall to the outside of the bin.
6. Route the end of the cable through the pipe handle, create a loop, and secure with a cable clamp.
7. Test the sweep stop (see
Section 6.17 – Testing on page 61
) and make any adjustments if necessary.
Figure 56.
Route the Cable
3-1/8"
(79 mm)
EASYFLOW2 (100 SERIES) – FARM TUBE BIN UNLOAD SYSTEM