6. Assembly
Before continuing, ensure you have completely read and understood this manual’s
Safety section, in addition to the safety information in the section(s) below.
6.1. Assembly Safety
• Do not take chances with safety. The components can be large, heavy, and hard to handle.
Always use the proper tools, rated lifting equipment, and lifting points for the job.
• Carry out assembly in a large open area with a level surface.
• Always have two or more people assembling the bin unload.
• Make sure you have sufficient lighting for the work area.
• Tighten all fasteners according to their specifications. Do not replace or substitute bolts,
nuts, or other hardware that is of lesser quality than the hardware supplied by the
manufacturer.
6.2. Bin Floor Preparation
1. Locate the center of the bin by measuring and drawing horizontal lines across the bin (see
Important
The center point must be found accurately to ensure that the sweep does not interfere with the bin
wall.
2. The vertical gearbox shaft in the center sump is aligned with the bin center point later in the assembly.
Note
The aeration floor planks should not be installed until the underfloor auger is installed.