Locating the Bin Center
6.3. Install the Underfloor Auger
If you are installing the underfloor auger
before
completion of the sidewall and anchoring the bin to the
foundation:
• Move the underfloor auger into nearly its final position in the bin before the final sidewall tier is complete.
• Cut an opening in the appropriate bin sheet before the sheet is installed (see
).
• After the bin sidewall has been completed and anchored to the foundation, according to the principles given
in
Section 6.3.1 – Install by Removing the Bin Sheet on page 27
, perform final positioning and leveling of the
underfloor auger, installing the anchor legs, and anchoring the underfloor auger.
If you are installing the underfloor auger
after
anchoring the bin sidewall to the foundation, follow either
Section 6.3.1 – Install by Removing the Bin Sheet on page 27
or
Section 6.3.2 – Install by Cutting a Bin Sheet in
according to the conditions given within those sections.
6.3.1 Install by Removing the Bin Sheet
This procedure describes removing a bin sheet after the bin sidewall has been anchored to the foundation and
applies to the installation of the underfloor auger
below the main door in a Westeel or Twister bin only
. You
must receive written permission from your bin manufacturer
if you want to use this procedure for:
• removing sidewall sheets other than below the main door for Westeel or Twister bins, or
• removing any sidewall sheets for bin manufacturers other than Westeel or Twister.
EASYFLOW2 (100 SERIES) – FARM TUBE BIN UNLOAD SYSTEM