1316-900 Revision AA
10kW Precision Calorimeter
11
Check the Location Where the Unit Will Be Installed
1.
Make sure the surface is level. An unbalanced system rack can produce faults and/or
inaccuracies.
2.
Select a spacious area with good airflow. Avoid placing the unit next to heat producing
equipment or in locations subject to drafts or sudden changes in temperature. Free flowing air
through the intake and outlet are important. Notice the air intake in Figure 5a below.
3.
Lock caster wheels once location is determined.
Figure 5a: Airflow
Typical Equipment List
The following equipment is required to complete the calibration:
•
TEGAM 1316A, RF High-Power Calorimeter
•
TEGAM 1300-912, Voltage/Current RF Adapter Assembly
•
Preen AFV+ 31015 (optional model), High Power Programmable AC Power Source
•
Zimmer L64-BAS (optional model), Precision Power Analyzer
•
Solid State Cooling Systems 1316-388, Thermorack Solid State Chiller (1 kW)
•
Orion 1316-389 (optional model), DC Inverter Chiller (12 kW)
•
TEGAM HPC-CAL, Automated Calorimeter Calibration Software
WARNING:
High voltage, current, and RF power are present in the system at
various times throughout this procedure. This procedure should only be performed by
qualified personnel sufficiently trained in the safe operation of high voltage, current,
and RF power systems. Failure to follow these precautions may result in death or
bodily injury, or equipment damage.