B5C Operation And Maintenance Manual
85950-301-000 RA
Aug. 05, 2016
17
3.7 Menu “4_OUT TEST”
During system installation and testing, it may be necessary to force relays and buzzers on
and off.
The Relay Testing feature allows the user to force the actuation of each relay. This
function forces an Actuate vs. De-actuate action, not an energized vs. non-energized
action. Therefore the user must be aware of these relays, which have been defined as
normally energized or not normally energized.
The 4mA (1VDC/2VDC) and 20mA (5VDC/10VDC) outputs can be tested too.
Up
F2
RETURN
TO MAIN MENU
MENU: TESTING:
1. TEST RELAY1
PRE NEXT ENTER
1. TEST RELAY1
OFF
ON OFF EXIT
F3
F3
F1
F2
1. TEST RELAY1
ON
ON OFF EXIT
Up
MENU: TESTING:
2. TEST RELAY2
PRE NEXT ENTER
2. TEST RELAY2
OFF
ON OFF EXIT
F3
F3
F1
F2
2. TEST RELAY2
ON
ON OFF EXIT
F1
Up
F2
MENU: TESTING:
3. TEST RELAY3
PRE NEXT ENTER
3. TEST RELAY3
OFF
ON OFF EXIT
F3
F3
F1
F2
3. TEST RELAY3
ON
ON OFF EXIT
Up
MENU: TESTING:
4. TEST BUZZER
PRE NEXT ENTER
4.TEST BUZZER
OFF
ON OFF EXIT
F3
F3
F1
F2
4.TEST BUZZER
ON
ON OFF EXIT
F1
F2
F1
Up
F2
MENU: TESTING:
5. TEST 4MA
PRE NEXT ENTER
5. TEST 4MA
OFF
ON OFF EXIT
F3
F3
F1
F2
5. TEST 4MA
ON
ON OFF EXIT
Up
MENU: TESTING:
6. TEST 20MA
PRE NEXT ENTER
6.TEST 20MA
OFF
ON OFF EXIT
F3
F3
F1
F2
6.TEST 20MA
ON
ON OFF EXIT
F1
F2
F1
MENU: TESTING:
EXIT TESTING
PRE NEXT ENTER
F2
F1
F2
F1
VDC OUTPUT CAN BE TESTED AT THE SAME TIME AS
TESTING 4/20MA:
WHEN OUTPUT 4MA, THE VDC OUTPUTS 1V OR 2V
WHEN OUTPUT 20MA THE VDC OUTPUTS 5V OR 10V
4mA and 20mA TEST ONLY IN Q5