Inverter (present on variable speed machines)
This component is a frequency converter for asynchronous three-phase motors that manages the
acceleration and deceleration ramps.
Warning!
The machine leaves the factory pre-configured. Do not modify inverter configurations as
doing so may cause risk to persons.
When the device is powered, the power components and some control components are connected
to the power supply line and touching them is extremely dangerous. The cover must remain closed.
In general, power must be disconnected before performing any operations on electrical or
mechanical parts.
After the ALTIVAR inverter has been switched off and the display is completely off, wait 15 minutes
to work on devices safely. These 15 minutes are required to discharge the capacitor
ALTIVAR 12 DIAGNOSTICS AND TROUBLESHOOTING
The messages displayed on the ALTIVAR12 inverter display listed in the table below block the inverter. The
cause of the displayed defect must be eliminated before resetting the inverter. It is possible to reset the
inverter by disconnecting and subsequently repowering.
Table 3 - ALTIVAR 12 (ATV12) Diagnostics
CODE ON
DISPLAY
DESCRIPTION
SOLUTION
----
FIRMWARE PROBLEM
REPLACEMENT
CFF
CONFIGURATION DEFECT
RERUN INVERTER CONFIGURATION AS DESCRIBED IN THE NEXT
PARAGRAPH
CFI
INVALID CONFIGURATION
CrF 1
LOAD CIRCUIT FAULT
SWITCH THE VARIATOR OFF AND BACK ON
CHECK CONNECTIONS
CHECK NETWORK POWER STABILITY
REPLACE THE PREVIOUS POINTS IF INEFFECTIVE
InF 9
CURRENT MEASUREMENT
ERROR
REPLACEMENT
InF b
INTERNAL TEMPERATURE
SENSOR FAULT
REPLACEMENT
InF E
CPU ANOMALY
SWITCH THE VARIATOR OFF AND BACK ON
REPLACE THE PREVIOUS POINT IF INEFFECTIVE
ObF
OVERBRAKE
CHECK POWER SUPPLY; IT MUST BE 20% BELOW MAXIMUM DURING
OPERATION
OCF
OVERCURRENT
EXCESSIVE LOAD
MECHANICAL LOCKING, CHECK MECHANICAL CONDITIONS
CHECK VARIATOR EARTH CONNECTION, MOTOR CABLE AND MOTOR
INSULATION
OHF
VARIATOR OVERHEATING
CHECK MOTOR LOAD, VENTILATION AND ROOM TEMPERATURE. WAIT
FOR THE VARIATOR TO COOL DOWN BEFORE STARTING IT BACK UP
OLC
OVERLOADING CURRENT
CHECK MECHANICS (WEAR, MECHANICAL LOCKING, OBSTACLES)
OLF
MOTOR OVERLOADING
CHECK MOTOR LOAD. WAIT FOR IT TO COOL, REMOVE INVERTER
POWER AND THEN REPOWER.
OPF 1
OUTPUT PHASE 1 LOSS
CHECK CONNECTIONS BETWEEN VARIATOR AND MOTOR
IF USING A CONTACTOR DOWNSTREAM, VERIFY THE ACCURACY OF
THE CONNECTION, THE CABLE AND CONTACTOR
OPF 2
OUTPUT PHASE 3 LOSS
OSF
OVERVOLTAGE
VERIFY NETWORK POWER
SCF 1
MOTOR SHORT-CIRCUIT
CHECK VARIATOR CABLE CONNECTIONS TO THE MOTOR AND MOTOR
INSULATION
SCF 3
SHORT-CIRCUIT TO EARTH
SCF 4
IGBT SHORT
REPLACEMENT
SCF 5
LOAD SHORT-CIRCUIT
CHECK CABLES CONNECTING THE VARIATOR TO THE MOTOR AND
MOTOR INSULATION
t
┘
F
IGBT HEATING
WAIT FOR IT TO COOL BEFORE STARTING UP AGAIN
USF
UNDERVOLTAGE
CHECK POWER
Содержание RPSP
Страница 1: ...Supra Linea Inclined Platform Lift Installation Manual INS RPSP EN 05 ...
Страница 6: ...5 Installation Manual RPSP INS RPSP EN 05 Fig 2 General exploded view ...
Страница 7: ...6 Installation Manual RPSP INS RPSP EN 05 Fig 3 Register exploded view ...
Страница 8: ...7 Installation Manual RPSP INS RPSP EN 05 Fig 4 View of the guide ...
Страница 9: ...8 Installation Manual RPSP INS RPSP EN 05 Fig 5 Machine body ...
Страница 11: ...10 Installation Manual RPSP INS RPSP EN 05 Fig 7 Platform Fig 8 Lateral Motorized Flap SML ...
Страница 12: ...11 Installation Manual RPSP INS RPSP EN 05 Fig 9 Frame crush proofing Fig 10 Anti impact ...
Страница 14: ...13 Installation Manual RPSP INS RPSP EN 05 Fig 12 Three phase electrical motor connections ...
Страница 57: ...56 Installation Manual RPSP INS RPSP EN 05 ...
Страница 58: ...57 Installation Manual RPSP INS RPSP EN 05 ...
Страница 60: ......