Installation –
Positioning the EMH9999 foundation and installing the POLEMHx |
15
In addition, you will need the following tools:
Torque spanner, spanner size
17 mm
Spirit level
Phillips screwdriver
Hexagon screwdriver
Torx screwdriver
Tape measure
Bricklaying tools
Concrete screed (mixed)
Positioning the EMH9999 foundation and installing the POLEMHx
The optional EMH9999 concrete foundation from ABL provides a level installation surface for all POLEMHx mounting
poles and ensures the necessary stability and support via factory-inserted screw anchors.
The following working steps are always identical, regardless of the mounting pole in question.
WARNING!
Creating a custom foundation
The calculation, design and manufacture of the self-made concrete foundation are the sole responsibility of the
operator or the company carrying out the installation on behalf of the operator.
DANGER!
Dangerous electrical currents
Always observe the 5 safety rules:
1
Cut power source
2
Secure all cut-off devices
3
Verify absence of voltage
4
Ground and short-circuit
5
Cover or bar access to adjacent components under voltage
The supply cable must not be reconnected to the electricity grid until
Step 4
in the section “Electrical connection
Proceed as follows:
1
Dig a ditch suitable for the EMH9999 foundation
(recommended: 120 × 120 cm).
y
Take into account the dimensions of the foun-
dation (H × W × D: 650 × 430 × 190 mm) as well
as a levelling layer (crushed rock/gravel) and a
cement mortar layer of about 10 cm under the
foundation.
120
75
120