5 - Installation
C
onnection to the AC side terminal block
To avoid risks of electrical shock, all wiring operations must be carried out with the dis-
connect switch downstream of the inverter (grid side) off.
The connection of the AC output cable to the inverter is performed by
means of the AC cable gland
10
and the dedicated AC output terminal
block
13
, by doing the following.
• Strip 18 mm of sheathing from the AC grid connection cables.
• Plug the AC line cable into the inverter, passing it through the AC cable
gland
10
.
10
The procedure for opening the contacts of AC output terminal block
13
and tightening cables is as follows:
1) Insert a flat screwdriver in the slot behind the contacts until the clamp
opens.
2) Insert the cable in the clamp with the screwdriver inserted in the slot.
3) Remove the screwdriver and check the tightness.