Section 5
Mounting
5.1
Required tools
GUID-B9478208-286B-4CFF-9C47-074D641A6F71 v2
Generally, all the screws included in delivered mounting kits are of Torx type and a torque
screwdriver of the same type is needed (Tx10, Tx15, Tx20, Tx25 and Tx30).
Use only the screws included in the mounting kit when mounting the plates and the
angles on the IED. Screws with wrong dimension may damage the PCBs inside the
IED.
5.2
Checking environmental conditions and mounting
space
GUID-2AF46E8C-25B3-4606-A768-E4B70E3D6B0A v12
The mechanical and electrical environmental conditions at the installation site must be within the
limits described in the technical manual and IEC60255-1, normal environment.
•
Avoid installation in dusty, damp places and where combustible materials are present near the
IED
•
Check that sufficient space is available.
Sufficient space is needed at the front and rear of the IED to allow access to wires and optical
fibers and to enable maintenance and future modifications.
•
Ensure convection cooling around the case to minimize the heating effect within the IED.
5.3
Mounting the IED
M11978-3 v12
The IED can be rack and wall mounted with the use of different mounting kits, see figure
.
An additional box of type RHGS can be mounted to one side of a 1/2.
The different mounting kits contain all parts needed including screws and assembly instructions. The
following mounting kits are available:
•
19” Panel (rack) mounting kit
•
Wall mounting kit
•
Side-by-side mounting kit
The mounting kits are ordered with the IED from the ordering sheet in the
Product
guide
. They are also available for ordering in the
Accessories guide
.
1MRK 514 030-UEN Rev. C
Section 5
Mounting
Switchgear control unit SAM600-IO
13
Installation manual
© 2017 - 2021 Hitachi Power Grids. All rights reserved