I N S TA L L AT I O N , O P ER AT I O N S A N D M A I N T EN A N C E M A N UA L
Put a mark on the torque bolts so you can visually
check whether the fastener has been properly
torqued. Repeat this process for all of the
horizontal bus splices, including the neutral
bus if provided.
If the Main Bus is insulated replace the insulation
boots for all of the horizontal bus splices; the
flexible boot is wrapped around the splice
connection and is secured with plastic tights.
Slide the cover, it is used to segregate the splice
kits for the main busbar joints and the C-profiles
of the back of the structure, this are located on the
C-profiles right in the area to separate the C-profile
and the splice kits. On a MCC Arc Resistant the
cover is made of GPO3.
—
34
—
35
—
36
—
34 Frame connection
using spacer bolts
—
35 Insulated main bus
Standard
Arc