Startup Operation
28 - EN
ProcessMaster / HygienicMaster
CI/FEP300/FEH300-EN
4 Startup
Operation
4.1
Preliminary checks prior to start-up
The following points must be checked before commissioning:
• The supply power must be switched off.
• The supply power must match information on the name plate.
• The pin assignment must correspond to the connection diagram.
• Sensor and transmitter must be grounded properly.
• The temperature limits must be observed.
• The sensor must be installed at a largely vibration-free location.
• The housing cover must be sealed before switching on the supply power.
4.2 Operation
4.2.1 Menu
navigation
M00024
4
3
2
1
Fig. 35
• The
◄
(1),
►
(4),
▲
(2) and
▼
(3) buttons are available for the menu-controlled
configuration.
• The menu/submenu name is displayed above in the LCD display.
• The number/line of the currently selected menu item is displayed in the upper right of the
LCD display.
• A scroll bar is located on the right edge of the LCD display which shows the relative position
of the currently selected menu item within the menu.
• Both of the
◄
and
►
buttons can have various functions assigned to them. The meaning of
these buttons is displayed below in the LCD display above the respective button. The
following functions are possible.
Содержание HART FEH300
Страница 2: ......
Страница 39: ...Appendix CI FEP300 FEH300 EN ProcessMaster HygienicMaster EN 37 ...
Страница 40: ...Appendix 38 EN ProcessMaster HygienicMaster CI FEP300 FEH300 EN ...
Страница 41: ......