IEC10000172.vsd
IEC10000172 V1 EN
Figure 75:
Configuring hardware channels directly to the function blocks
IEC10000173.vsd
IEC10000173 V1 EN
Figure 76:
CMT: Hardware channels appearing in the Communication
Management Tool
2. Right-click the IED in the plant structure and select
Communication
Management
to start the Communication management tool.
3. Select the DNP3 protocol from the new window and click
OK
presents the design of the two container windows, which open after the
selection of DNP3.
•
The right window shows tabs for possible communication channels.
•
The left window has a drop down menu for signal selection and buttons
for signal movement, see
.
1MRK 511 261-UEN -
Section 9
DNP3 communication engineering
650 series
107
Engineering Manual